WESTWATER RESOURCES, INC. annual report, FY2022

Westwater Resources, Inc. — FY 2022 Form 10-K

Reporting period: Fiscal year ended December 31, 2022; filed March 6, 2023. Westwater is developing a U.S. battery-grade natural graphite business and had no operating revenue in the year. It has not recorded revenue from operations since 2009.

Business context and developments

  • Westwater continued construction of Phase I of the Kellyton Graphite Plant in Alabama, including site work, foundations, utilities, manufacturing buildings and delivery of some long-lead equipment. The company reported all permits needed to complete Phase I construction had been obtained.
  • Phase I was optimized to planned annual capacity of 7,500 metric tons of coated spherical purified graphite (ULTRA-CSPG) and 8,500 metric tons of SPG fines. The company plans to purchase third-party graphite feedstock until its Coosa deposit is developed.
  • The Coosa deposit resource estimate comprises 26 million short tons of indicated resources at 2.89% graphitic carbon and 97 million short tons of inferred resources at 3.08%. These are mineral resources, not reserves, and do not demonstrate economic viability.

Financial performance and position

MetricFY 2022 / Dec. 31, 2022FY 2021 / Dec. 31, 2021
RevenueNo operating revenueNo operating revenue
Net loss$11.1 million; $0.25 per share$16.1 million; $0.49 per share
Operating expenses$12.1 million$18.2 million
Cash used in operating activities$13.2 million$16.9 million
Cash used in investing activities$52.8 million$2.1 million
Cash provided by financing activities$25.9 million$84.0 million
Cash and cash equivalents$75.2 million$115.3 million
Total assets$168.4 million$133.0 million
Total liabilities$26.4 million$6.8 million
Stockholders’ equity$142.0 million$126.2 million

Margins are not meaningful because the company had no operating revenue. The balance sheet reports no debt balance; current liabilities were $25.1 million, including $23.0 million of accounts payable. Net working capital was approximately $51.0 million. The auditor reported substantial doubt about the company’s ability to continue as a going concern: planned non-discretionary spending through March 2024 exceeds available cash, absent financing or use of equity facilities.

Material changes versus FY 2021

  • Net loss narrowed by $5.0 million, mainly because product development and arbitration costs fell and interest income rose. General and administrative expenses increased by about $1.0 million.
  • Product development expense fell to $1.1 million from $6.0 million, while arbitration expense declined to $0.1 million from $2.2 million. Other income rose to $1.0 million, primarily from interest income.
  • Capital expenditures for Kellyton drove investing cash outflow to $52.8 million. Financing inflows fell to $25.9 million from $84.0 million as the company sold approximately 13.0 million shares through its at-the-market facility in 2022.
  • Year-end shares issued increased to 48.4 million from 35.3 million. The company’s equity financing supported operations and plant development but diluted existing shareholders.

Outlook, risks and unusual items

  • Phase I construction is estimated to cost approximately $271 million, up from the original $202 million estimate. The company reported $76.4 million incurred, inclusive of year-end liabilities, and estimated approximately $215.7 million of remaining capital expenditures. These figures and schedules are subject to change.
  • Management expected testing and commissioning in late 2023 and first production in the first half of 2024, conditional on securing additional funding; Phase I optimization was targeted for the second half of 2024. Phase II is planned to raise annual capacity to 40,500 metric tons of ULTRA-CSPG and 46,000 metric tons of SPG fines.
  • On March 6, 2023, the company signed a non-binding, non-exclusive indicative term sheet for $150 million of private debt financing, anticipated to close in Q2 2023 subject to due diligence and final terms. Closing, amount and sufficiency are not assured.
  • Customer activity included five letters of intent, subject to customary conditions and future definitive agreements, and a collaboration agreement with a Tier 1 EV battery manufacturer to evaluate product suitability. These do not constitute confirmed sales commitments.
  • On March 3, 2023, an arbitration tribunal found Turkey had unlawfully expropriated Westwater’s Turkish investment and awarded approximately $1.3 million in damages, about $3.7 million in arbitration costs and expenses, plus interest yet to be determined. The award was not recognized in the 2022 financial statements; recognition depends on collection being probable.
  • Key risks include financing availability and dilution, construction cost and schedule overruns, inflation and supply-chain constraints, successful commissioning and commercial-scale production, customer qualification and sales, graphite price volatility, and permitting and development risks for the Coosa mine. The Taylor litigation remains unresolved; the plaintiff seeks CAD $3.0 million plus other relief, and Westwater has counterclaimed for CAD $7.0 million plus other relief.

Important facts for investors to verify

  • Whether the proposed $150 million financing closed on final terms and provides sufficient funds to complete Phase I.
  • Updated construction cost, remaining funding requirement, construction progress and commissioning/production schedule.
  • Whether customer testing converts into definitive, enforceable supply agreements and what volumes and terms they contain.
  • Collection prospects, timing and interest calculation for the Turkey arbitration award; no award proceeds were recognized at year-end.
  • Any updated feasibility, permitting, surface-access and financing plans for Coosa; disclosed resources are not reserves and have no demonstrated economic viability.
  • Progress against the going-concern funding risk and the effect of further equity issuance on cash runway and shareholder dilution.