Cheniere Energy Partners, L.P. current report, 11 December 2011

Business Context and Reporting Period

This Form 8-K Current Report was filed by Cheniere Energy Partners, L.P. on December 11, 2011. The filing discloses the entry into a material definitive agreement: an LNG Sale and Purchase Agreement (SPA) between Sabine Pass Liquefaction, LLC (a subsidiary of Cheniere Partners) and GAIL (India) Limited.

Key Financial Metrics and Contract Terms

The filing details a long-term LNG supply contract rather than reporting period financial results. Key contractual metrics include:

  • Primary Volume: 182,500,000 MMBtu annually (approx. 3.5 million tonnes per annum) commencing with the first commercial delivery from the fourth liquefaction train.
  • Interim Volume: 10,400,000 MMBtu annually (approx. 0.2 mtpa) from the second train's commercial operation until the fourth train's first delivery.
  • Contract Term: 20 years, with an option for GAIL to extend for up to 10 additional years.
  • Pricing Formula: $3.00 fixed component plus 115% of the NYMEX Henry Hub natural gas futures settlement price for the delivery month. The fixed portion is subject to annual inflation adjustments.

Material Changes and Conditions

The agreement is subject to several material conditions precedent before obligations become effective:

  • Receipt of all regulatory approvals for the fourth liquefaction train in Cameron Parish, Louisiana.
  • Securing necessary financing arrangements.
  • A positive final investment decision (FID) by Sabine Liquefaction.
  • Effectiveness of export authorizations permitting LNG exports from the United States.
  • Conditions must be satisfied or waived by June 30, 2013, or a later date agreed upon by the parties.

Outlook, Risks, and Termination Provisions

The filing outlines specific risks and termination rights for both parties:

  • Force Majeure: GAIL may terminate if force majeure events aggregate 24+ months in a 36-month period, causing a 50%+ reduction in available LNG (100% prior to first delivery).
  • Performance Failures: Termination rights exist if Sabine Liquefaction fails to deliver 50% of scheduled cargoes in a 12-month period or if the fourth train does not commence operations within 180 days of the designated date.
  • Buyer Default: Sabine Liquefaction may terminate if GAIL fails to take 50% of scheduled cargoes, fails to provide required guarantees, or violates trade laws.
  • Financial Default: Either party may terminate if the other fails to pay amounts due exceeding $75 million or declares bankruptcy.

Investor Verification Checklist

  • Verify the status of regulatory approvals and export authorizations for the fourth liquefaction train.
  • Confirm the timeline for the Final Investment Decision (FID) and financing arrangements.
  • Monitor the June 30, 2013 deadline for satisfying conditions precedent.
  • Review the full text of the SPA (Exhibit 10.1) for detailed exceptions and qualifications not summarized in the 8-K.
  • Assess GAIL's creditworthiness and ability to provide required guarantees.