NOVAGOLD RESOURCES INC quarterly report, Q2 FY2020

NOVAGOLD RESOURCES INC. — Q2 2020 Form 10-Q

Reporting period: Three and six months ended May 31, 2020. Financial amounts below are in U.S. dollars; financial statement amounts are in thousands unless stated otherwise. NOVAGOLD is an exploration and development company with a 50% interest in the Donlin Gold project in Alaska, owned equally with Barrick. The company had no revenue from its planned principal business.

Financial performance and liquidity

MetricThree months 2020Three months 2019Six months 2020Six months 2019
General and administrative expense$4.387 million$4.215 million$9.101 million$8.555 million
Equity loss — Donlin Gold$3.700 million$2.198 million$5.268 million$3.521 million
Loss from operations$8.087 million$6.413 million$14.369 million$12.076 million
Net loss$7.233 million$5.515 million$13.828 million$11.838 million
Basic and diluted loss per share$0.02$0.02$0.04$0.04
Cash used in operating activities$1.834 million$1.761 million$5.331 million$4.911 million

Revenue and operating margins are not applicable because NOVAGOLD reported no operating revenue. For the quarter, lower interest income and higher operating losses were partly offset by lower promissory-note interest expense and foreign-exchange movements.

  • Liquidity: At May 31, cash and cash equivalents were $53.329 million and term deposits were $81.000 million, totaling $134.329 million. Total assets were $235.031 million; total liabilities were $110.695 million.
  • Cash use: In the first six months, cash and cash equivalents declined $14.220 million. Cash used included $5.331 million in operating activities, $6.890 million in Donlin funding and $1.652 million of withholding taxes on vested performance share units; foreign exchange reduced cash by $0.347 million.
  • Debt: The Barrick promissory note had a carrying value of $106.947 million, including $51.576 million principal and $55.371 million accrued interest. It accrues interest at U.S. prime plus 2% and is payable from 85% of NOVAGOLD’s share of future Donlin mine revenue or from certain proceeds from reducing its Donlin interest. A 1% change in prime would change annual accrued interest by about $1.1 million, all else equal.
  • Other significant asset: Notes receivable from Newmont had a $94.327 million carrying value, including accretion. A further contingent $75 million note was assigned no value because construction approval for Galore Creek was not considered probable.

Changes and operating developments

Compared with 2019, quarterly operating loss increased $1.674 million and net loss increased $1.718 million. For the six-month period, operating loss rose $2.293 million and net loss rose $1.990 million. Management attributed the increases mainly to higher Donlin costs from the 2020 drilling program and higher general and administrative costs; lower interest income also contributed to the net-loss increase. Donlin funding was $6.890 million in the first half, versus $3.806 million a year earlier.

COVID-19 precautions temporarily paused Donlin’s drill program and placed the site into care and maintenance from April until mid-May. Drilling restarted in late May, with four drills operating at the time of the filing. The company reported that its share of the 2020 Donlin work program and budget was $20 million, including $11 million for drilling.

Donlin received certain State of Alaska transportation-related permits and a pipeline right-of-way lease in early 2020. The pipeline lease was subsequently sent for reconsideration, including further analysis of cumulative effects. Separately, an appeal concerning the project’s water-quality certification proceeded to a conditionally granted adjudicatory hearing in June 2020. The filing also describes ongoing permitting work and administrative appeals concerning project approvals.

Outlook, risks and contingencies

  • Management expected 2020 spending of approximately $31 million: $20 million for NOVAGOLD’s share of Donlin expenditures and $11 million for general and administrative costs. Management believed available cash and term deposits were sufficient for anticipated project funding and corporate costs.
  • Additional capital would be required if Donlin proceeds to engineering and construction. The company has no operating cash flow and said continued operations depend on financing or future cash flows; construction funding was expected to require debt, equity, project-specific debt or other sources.
  • A construction decision depends on further engineering, approval of a construction program and budget by the Donlin joint-venture board, permits, financing, commodity prices and other factors. COVID-19 could affect personnel, travel, drilling, testing and schedules.
  • The filing identifies risks including permitting delays or litigation, public opposition, project development and financing uncertainty, commodity and market conditions, and COVID-19. Management reported no material current, pending or threatened litigation, while separately describing the Donlin permit-related proceedings.
  • U.S. investors should note the disclosed potential PFIC tax status: the company believed it was not a PFIC for fiscal 2019 but said it may become one in future years, including depending on proposed IRS regulations.

Important facts for investors to verify

  • Progress and timing of Donlin’s drilling, engineering, permitting proceedings and any joint-venture construction decision.
  • Whether the $134.329 million of cash and term deposits remains adequate against spending needs, and the terms and availability of future construction financing.
  • Changes in the Barrick note’s accrued interest and the company’s ability to fund Donlin without operating revenue.
  • COVID-19 effects on project activity and the status of the water-quality certification and pipeline right-of-way reconsideration.
  • Potential dilution: as of June 17, 2020, 329,597,770 common shares were outstanding, with a maximum 14,414,653 additional shares issuable upon exercise or payout of disclosed options and share units.