NOVAGOLD RESOURCES INC quarterly report, Q1 FY2017

NOVAGOLD RESOURCES INC. — Q1 2017 Form 10-Q

Reporting period: Three months ended February 28, 2017; comparative period ended February 29, 2016. Amounts below are U.S. dollars. The company explores and develops gold and copper properties, principally through 50% interests in the Donlin Gold project in Alaska and the Galore Creek project in British Columbia. It reported no realized revenue from its principal business.

Key financial metrics

MetricQ1 2017Q1 2016 / comparison
RevenueNoneNone
Operating loss$9.0 million$9.5 million
Net loss$10.1 million$10.0 million
Net loss per share, basic and diluted$0.03$0.03
Operating cash used$4.4 million$7.7 million
Cash and cash equivalents at period end$18.2 million$30.3 million at Nov. 30, 2016
Term deposits at period end$80.0 million$75.0 million at Nov. 30, 2016
Promissory note carrying value$86.0 million$84.8 million at Nov. 30, 2016
Total assets / total equity$405.3 million / $297.4 million$408.3 million / $300.3 million at Nov. 30, 2016

Cash, cash equivalents and term deposits totaled $98.2 million at quarter-end, down $7.0 million from fiscal year-end. Current liabilities were $1.5 million. No operating margin is meaningful because the company had no revenue. The filing does not present a conventional operating cash-flow or margin outlook.

The note payable to Barrick consists of $51.6 million principal plus $34.4 million accrued interest. It bears interest at U.S. prime plus 2% and is payable from 85% of NOVAGOLD’s share of future Donlin production revenue or net proceeds from a reduction of its project interest.

Material changes and operating developments

  • Operating loss narrowed by about $0.6 million year over year, mainly because general and administrative expense declined to $6.7 million from $7.3 million, including lower stock-option compensation.
  • Net loss increased by about $0.2 million, as lower operating costs were more than offset by a $0.7 million adverse change in foreign-exchange gains and losses.
  • Operating cash use fell by $3.3 million, primarily because less cash was paid for withholding taxes on vested performance share units. The company reported $7.7 million of net investing cash use, including $2.6 million of affiliate funding and a net $5.0 million purchase of term deposits.
  • NOVAGOLD funded Donlin Gold with $2.4 million and Galore Creek with $0.2 million during the quarter. Their respective investment balances were $1.3 million and $244.2 million.

Outlook, risks and contingencies

  • Management expects 2017 spending of approximately $23 million: $11 million for corporate and administrative costs, $10 million for Donlin Gold, and $2 million for Galore Creek. Management said current cash and term deposits should cover anticipated project funding and general and administrative costs through completion of Donlin permitting.
  • Donlin permitting and environmental review continued. The Army Corps of Engineers’ final environmental impact statement was anticipated in early 2018; additional permits, engineering, a construction budget approval and financing remain necessary before development. NOVAGOLD’s share of Donlin’s 2017 work program was expected to be about $10 million.
  • Galore Creek continued technical studies and care and maintenance. NOVAGOLD remains open to monetizing some or all of its 50% interest. Its expected 2017 contribution was about $2 million.
  • Management said additional capital would be required if Donlin receives permits and proceeds to engineering and construction. Financing may depend on debt, equity, project financing or other sources; there is no assurance financing will be available on acceptable terms or at all.
  • Key risks include permitting delays or denial, public opposition and litigation, project cost and financing uncertainty, commodity prices, dependence on joint-venture partners, and currency, credit and interest-rate exposure. A $0.01 change in the Canadian dollar was estimated to affect comprehensive income or loss by about $3.8 million; a 1% change in U.S. prime was estimated to change annual note interest by about $0.9 million.
  • Operating lease commitments totaled $326,000 through 2020. The company reported no material current, pending or threatened litigation and no material changes to its previously disclosed risk factors.

Important facts for investors to verify

  • Progress and timing of Donlin’s final environmental impact statement, permits, engineering work and construction decision.
  • Whether the stated $98.2 million of cash and term deposits remains sufficient as project spending and permitting needs evolve.
  • Donlin financing requirements, the terms and accrued interest of the Barrick promissory note, and any proposed financing or asset monetization.
  • Actual 2017 project and corporate spending versus management’s approximately $23 million outlook, including any additional joint Donlin studies.
  • Project cost, permitting, currency and commodity-price assumptions underlying management’s forward-looking statements.