Business Context and Reporting Period
The filing is a Form 10-Q for WPCS International Incorporated and Subsidiaries, not Fabric.AI, Inc. It covers the quarter and six months ended October 31, 2011, within fiscal 2012. WPCS provided design-build engineering services for communications infrastructure across wireless communications, specialty construction, and electrical power markets. The company reported more than 450 employees across six operating centers on three continents.
On September 1, 2011, WPCS sold its St. Louis and Sarasota operations to Multiband Corporation for $2.0 million in cash. These businesses are presented as discontinued operations for all periods shown.
Financial Metrics
| Metric | Three Months Ended October 31, 2011 | Six Months Ended October 31, 2011 |
|---|---|---|
| Revenue | $28.2 million | $51.7 million |
| Operating income (loss) | $(0.3) million | $0.1 million |
| Loss from continuing operations | $(0.7) million | $(0.3) million |
| Net loss attributable to WPCS | $(1.7) million | $(1.7) million |
| Net loss per share | $(0.24) | $(0.24) |
| Adjusted EBITDA, as defined by management | Approximately $0.4 million | Approximately $1.5 million |
- Six-month cost of revenue was $41.1 million, or 79.5% of revenue, compared with 81.6% in the prior-year period.
- Six-month selling, general and administrative expense was $9.3 million, or 18.0% of revenue, compared with 22.4% previously.
- Cash and cash equivalents were $5.2 million at October 31, 2011, compared with $4.9 million at April 30, 2011.
- Working capital was $14.6 million, based on current assets of $41.6 million and current liabilities of $27.0 million.
- Accounts receivable were $25.4 million, net of a $0.9 million allowance for doubtful accounts.
- Total liabilities were $27.2 million and total equity was $24.7 million at October 31, 2011.
- Operating activities provided $2.9 million of cash during the six months, compared with $1.4 million used in the prior-year period.
- Investing activities provided $1.4 million, primarily reflecting net proceeds from the sale of the discontinued operations, partly offset by $0.3 million of capital expenditures.
- Financing activities used $3.9 million, including $3.5 million of line-of-credit repayments and $0.4 million repaid to the China joint venture partner.
- At October 31, 2011, borrowings under the Bank of America line of credit were $3.5 million. The filing states that the balance was subsequently reduced to $2.4 million using a $1.1 million tax refund.
Material Changes Versus the Prior Comparable Period
- Six-month revenue increased 11% to $51.7 million from $46.5 million, driven by organic growth. Quarterly revenue increased 21% to $28.2 million from $23.2 million.
- Six-month operating results improved from a $7.6 million operating loss to $0.1 million of operating income. The prior-year period included a $4.3 million goodwill and intangible-asset impairment charge.
- Six-month net loss attributable to WPCS improved to $1.7 million from $6.3 million. The current period included a $1.3 million loss from discontinued operations, including a $1.0 million disposal loss.
- Adjusted EBITDA improved from a $1.6 million loss to approximately $1.5 million of positive EBITDA for the six months.
- Revenue mix shifted toward electrical power and specialty construction. For the six months, wireless communications represented 22.0% of revenue, specialty construction 7.2%, and electrical power 70.8%.
- Wireless communications revenue declined because of project delays and postponed public-sector awards. Specialty construction revenue increased primarily because of China operations, while electrical power revenue increased primarily because of the Trenton operations.
- Management attributed lower SG&A to cost-reduction measures, lower salaries, commissions, bonuses, and professional fees.
- Backlog declined to approximately $30.2 million at October 31, 2011, from $39.6 million at July 31, 2011, while the bid list increased to approximately $163 million from $127 million.
Guidance, Outlook, Risks, Contingencies, and Unusual Items
- Management expected continued positive EBITDA and a return to profitability during fiscal 2012, supported by cost reductions, delayed project revenue, additional bidding activity, and revenue enhancements. The filing states that achieving these objectives is necessary to support the company as a going concern.
- The company was in default under its Bank of America loan arrangements for failing to repay the line of credit in full by November 30, 2011 and for failing to make a required $75,000 forbearance payment. Bank of America was entitled to exercise remedies but had not demanded payment as of the filing.
- WPCS was negotiating another forbearance amendment and seeking replacement debt financing. There was no assurance that a waiver, modification, refinancing, or additional financing would be obtained on acceptable terms.
- If the line of credit were called and refinancing were unavailable, management stated that existing cash might not be sufficient to satisfy obligations as they became due.
- The company extended certain vendor payment terms and expected this practice to continue over the following twelve months.
- The China operations owed approximately $3.1 million to their joint venture partner, including $0.7 million due on demand. Management expected the partner to renew unpaid balances based on historical practice.
- Acquisition-related contingent consideration was $1.1 million at October 31, 2011, with a potential additional payment of approximately $0.9 million depending on Pride’s EBIT performance.
- The company had a shelf registration permitting the potential sale of up to 2,314,088 common shares, but no shares had been issued under it as of October 31, 2011.
- Multiband had a non-binding proposal to acquire WPCS at $3.20 per share and an exclusivity period through February 1, 2012. Completion required due diligence, a definitive merger agreement, financing, and shareholder approval.
- Shareholder litigation challenging the proposed Multiband transaction had been consolidated in Pennsylvania. The company and directors denied the allegations and intended to defend the action.
- Revenue recognition relies on percentage-of-completion estimates, including estimated costs to complete contracts. During the quarter, revisions to contract estimates reduced gross profit by approximately $1.4 million; the six-month impact was a $0.5 million reduction.
- The filing reported no off-balance-sheet arrangements. Management concluded that disclosure controls and procedures were effective at October 31, 2011.
Important Facts for Investors to Verify
- Confirm the issuer identity: the supplied filing is for WPCS International Incorporated, whereas the request metadata names Fabric.AI, Inc.
- Verify the status and ultimate resolution of the Bank of America default, forbearance negotiations, and any replacement financing.
- Assess whether positive EBITDA and management’s projected fiscal 2012 return to profitability were achieved.
- Review cash availability, including the approximately $1.9 million held in Australia, vendor payment extensions, and near-term obligations.
- Evaluate contract-estimate revisions, backlog conversion, project delays, customer concentration, and the large bid list relative to realized revenue.
- Verify the outcome of the proposed Multiband acquisition, shareholder litigation, and any related dilution or transaction costs.
- Consider the sustainability of earnings excluding the prior-year impairment charge and including the discontinued-operations disposal loss.