Ioneer Ltd annual report, Q4 FY2023

Ioneer Ltd. — Form 20-F summary

Period: Fiscal year ended June 30, 2023, with comparisons to fiscal 2022 and 2021. This is an annual report, not a 2022 Q4 filing; the supplied filing does not provide standalone Q4 results. Financial statements are prepared under IFRS and presented in U.S. dollars.

Business context and financial results

Ioneer is a development-stage company focused on its wholly owned Rhyolite Ridge lithium-boron project in Nevada. It has not started commercial production and reported no sales revenue. Ernst & Young audited the financial statements and gave an unmodified opinion.

Metric (US$ millions, except per-share data)FY2023FY2022FY2021
Sales revenueNoneNoneNone
Finance income3.3213.4860.218
Operating loss(9.696)(11.972)(6.680)
Net loss(6.391)(8.503)(14.042)
Operating cash used(8.069)(9.345)(4.848)
Investing cash used(32.472)(28.387)(17.670)
Cash at year end52.70994.17762.475
Basic loss per ordinary share(0.30) cents(0.42) cents(0.80) cents

At June 30, 2023, current assets were $53.062 million, current liabilities $8.842 million, total liabilities $8.920 million and net assets $197.399 million. Liabilities were primarily payables, provisions and lease liabilities; the filing reports no material borrowings outstanding. The DOE financing described below is proposed, not funded debt. Capitalized exploration and evaluation expenditure was $152.226 million. Capital expenditures were $33.6 million in FY2023, versus $32.0 million in FY2022 and $20.9 million in FY2021. Margins are not meaningful because there are no product sales.

Changes versus prior periods

  • Net loss narrowed by $2.112 million from FY2022, mainly as other expenses fell $3.215 million; employee benefits expense rose $0.911 million and finance income declined $0.165 million.
  • Cash decreased $41.468 million during FY2023, compared with increases in FY2022 and FY2021. FY2023 included $32.472 million of investing outflows and no share-issuance proceeds; FY2022 included substantial equity-raising proceeds.
  • Cash and short-term deposits fell to $52.709 million from $94.177 million. Management said existing working capital was expected to fund operations through October 31, 2024.
  • Effective July 1, 2022, Ioneer changed its presentation currency from Australian dollars to U.S. dollars; comparative periods were retrospectively presented in U.S. dollars.

Outlook, financing, and key risks

  • Management targeted construction commencement in the first half of calendar 2024, an approximately 24-month construction period, and first production in calendar 2026, assuming permits, financing and a final investment decision (FID) are secured. These are plans, not assured outcomes.
  • The April 2020 project development estimate was approximately $785 million and was to be updated before FID. A new Class II engineering estimate was expected in the second half of 2023.
  • Sibanye-Stillwater is expected to contribute $490 million for a 50% project interest, with Ioneer retaining operatorship and 50%. The joint venture remained conditional, with closing expected in calendar 2024 subject to FID, permits, financing and other conditions.
  • A DOE Loan Programs Office conditional commitment contemplated a loan of up to $700 million, with an approximately 10-year term. Amount, documentation and closing remained subject to negotiation and conditions, including a positive federal record of decision. Ioneer warned it could still need additional funding; any shortfall in project funding under the joint venture would be shared equally.
  • The federal NEPA review and BLM approval remained key outstanding steps. Nevada air-quality and water-pollution-control permits had been obtained. Tiehm’s buckwheat was listed as endangered in December 2022 and critical habitat designated; the mine plan was revised to avoid direct impacts and mitigate indirect impacts. Permitting, appeals, habitat protections and litigation could delay or impair development.
  • Binding lithium offtake agreements with EcoPro, Ford and PPES and boric-acid sales agreements were described, but are conditional on project development and FID. The filing estimates the lithium agreements cover about 87% of expected first three years’ production; boric-acid commitments cover 100% of expected first-year production and more than 85% in years two and three.
  • Other material risks include construction-cost escalation, technical and recovery assumptions, lithium and boron price volatility, access to capital, water and other permits, environmental obligations, and the possibility the project may not become commercially viable. Resource and reserve estimates depend on assumptions and are not guarantees of recoverable production.
  • Ioneer believed it was a passive foreign investment company (PFIC) for U.S. tax purposes in FY2023 and expected PFIC status for FY2024, potentially creating adverse U.S. tax consequences for investors.

Important facts for investors to verify

  • Whether the updated capital estimate, engineering work and project economics support FID, and how any funding gap will be covered.
  • Progress and final outcomes of the NEPA/BLM process, Tiehm’s buckwheat consultation, remaining permits and any third-party challenges.
  • Whether the DOE loan reaches definitive agreements and closes, and whether Sibanye-Stillwater’s joint venture conditions are satisfied on the stated timeline.
  • Cash burn and liquidity relative to management’s October 31, 2024 runway estimate, including subsequent financing or dilution.
  • Whether customer offtake conditions, product specifications, pricing terms and planned production volumes remain achievable.
  • Whether PFIC status applies for each relevant tax year; investors should consult their own tax advisers.