PERPETUA RESOURCES CORP. quarterly report, Q1 FY2024

Perpetua Resources Corp. — Q1 2024 Form 10-Q Summary

Business context and reporting period

Perpetua Resources is a British Columbia corporation focused on mineral exploration, permitting, environmental restoration, and development of the Stibnite Gold Project in Idaho. The company operates in one segment and had no commercial production or operating revenue during the three months ended March 31, 2024. The filing was signed May 10, 2024; 64,510,511 common shares were outstanding as of May 3, 2024.

Financial performance and liquidity

MetricQ1 2024Q1 2023Change
Operating loss$8.1 million$8.0 millionUp $0.1 million
Grant income$5.2 million$3.3 millionUp $1.9 million
Net loss$2.9 million$4.6 millionImproved $1.7 million
Basic and diluted loss per share$0.05$0.07Improved
Net cash used in operating activities$3.5 million$4.1 millionImproved $0.6 million
Cash and cash equivalents, period-end$8.0 million$18.6 millionDown $10.5 million

There was no commercial revenue, gross profit, or operating margin to report. Exploration expense increased 15% to $6.5 million, primarily because engineering costs rose by $2.5 million, partly offset by lower permitting and legal and sustainability costs. Environmental liability expense declined to $0.2 million from $1.1 million.

Investing activities provided $8.3 million, principally from the net proceeds of an $8.5 million Franco-Nevada silver royalty transaction. The company ended the quarter with $8.0 million of cash, $1.9 million of receivables, $2.7 million of trade and other payables, and total liabilities of $8.0 million. The filing does not report outstanding conventional debt; liabilities include $4.5 million of CWA settlement payments and $0.7 million of environmental reclamation liabilities.

Material changes versus the prior comparable period

  • Grant income increased due mainly to $2.6 million recognized under the Defense Production Act Technology Investment Agreement and $2.6 million under the DOD Ordnance Technology Consortium agreement. The latter did not exist in Q1 2023.
  • On March 21, 2024, the company received $8.5 million of gross proceeds from granting Franco-Nevada a perpetual royalty on future payable silver production; net proceeds of $8.3 million reduced the carrying value of mineral properties.
  • Exploration expense increased from $5.7 million to $6.5 million, while operating loss remained broadly stable because higher grant income offset higher operating expenditures.
  • Cash declined materially year over year despite the royalty proceeds, reflecting continued project and corporate spending and the company’s ongoing non-revenue status.
  • Common shares outstanding increased from 64.1 million at December 31, 2023 to 64.4 million at March 31, 2024, primarily from share-unit distributions.

Guidance, outlook, risks, contingencies, and unusual items

Management expects 2024 expenditures of approximately $50.1 million, including approximately $11.8 million for permitting, $14.4 million for corporate, project financing and administrative costs, $17.7 million for engineering and design, $5.2 million for field operations, and $1.0 million for early restoration. Approximately $37.0 million is expected to be funded through DPA reimbursements, with the remainder funded from cash on hand.

The DPA TIA was amended on May 2, 2024 to add $34.4 million, increasing total potential funding to $59.2 million. These funds are restricted primarily to permitting, environmental monitoring, technical studies, and construction-readiness activities and cannot fund certain corporate expenses, ASAOC obligations, or CWA settlement payments. Management expects approximately $13.2 million of additional DPA grant income in Q2 2024 and approximately $0.5 million of additional DOTC grant income.

The company’s liquidity forecast indicates that cash resources available for expenses not eligible for DPA reimbursement may be exhausted in the fourth quarter of 2024. Management states that additional financing is required and that substantial doubt exists regarding the company’s ability to continue as a going concern for one year after issuance of the interim financial statements. Potential funding sources include equity, project or corporate debt, additional government funding, and other financing, but no financing is assured. The $20.0 million ATM program had $17.2 million remaining capacity at March 31, 2024, and no shares were sold under it during the quarter.

The USFS schedule anticipates publication of the FEIS and Draft Record of Decision in Q2 2024 and a Final Record of Decision in Q4 2024, although the schedule is not binding and may be delayed or produce an unfavorable outcome. Ancillary permits remain in process, including water quality, wetlands, cyanidation, air, discharge, and water-rights approvals.

In April 2024, EXIM issued a non-binding, conditional letter of interest for potential financing of up to $1.8 billion. Any financing remains subject to an application, due diligence, underwriting, approvals, environmental review, and final terms; it is not committed funding.

The CWA settlement requires $5.0 million of payments over four years. The company paid $0.5 million during Q1 2024 and had $4.5 million remaining payable at March 31, 2024. It also spent $0.2 million on ASAOC cleanup activities and estimated $0.7 million of remaining 2024 environmental work.

Key risks include permitting and litigation outcomes, access to capital, restricted use of government funding, cost overruns and inflation, gold and antimony prices, environmental liabilities, execution of construction-readiness activities, and the fact that the project’s deposits had not yet met the SEC definition of proven reserves. The company reported effective disclosure controls and no material changes in internal control over financial reporting.

Important facts for investors to verify

  • Whether the company secures additional unrestricted financing before projected cash exhaustion in Q4 2024.
  • The timing and outcome of the FEIS, Draft ROD, Final ROD, and related ancillary permits.
  • The terms, eligible uses, reimbursement timing, and remaining availability of the $59.2 million DPA TIA and the $15.5 million DOTC award.
  • Whether the conditional EXIM letter of interest develops into committed project financing.
  • The company’s ability to fund the remaining $4.5 million CWA settlement obligation, approximately $0.7 million of remaining 2024 ASAOC work, and other unrestricted corporate expenses.
  • Future dilution from the ATM program and equity-based compensation.
  • Updated project economics, reserve classification, capital requirements, and commodity-price assumptions before any construction or production decision.