Intrepid produces and sells potash, langbeinite marketed as Trio®, and by-products from five active facilities in New Mexico and Utah. The company is developing the HB Solar Solution mine in New Mexico. This unaudited filing covers the quarter and nine months ended September 30, 2013, compared with the corresponding 2012 periods.

Key financial metrics

MetricQ3 2013Q3 20129M 20139M 2012
Sales$70.6 million$129.4 million$262.5 million$340.4 million
Gross margin$12.9 million$51.9 million$74.8 million$133.0 million
Gross margin percentage18.3%40.1%28.5%39.1%
Operating income$1.7 million$43.6 million$45.8 million$107.3 million
Net income$2.0 million$33.3 million$28.3 million$72.9 million
Diluted EPS$0.03$0.44$0.37$0.97
Cash flow from operations$14.7 millionNot separately provided in filing text$62.1 million$132.3 million
  • Q3 operating margin was approximately 2.4%, versus 33.7% in the prior-year quarter; nine-month operating margin was approximately 17.5%, versus 31.5%.
  • Q3 net margin was approximately 2.9%, versus 25.7%; nine-month net margin was approximately 10.8%, versus 21.4%.
  • Q3 potash sales volume fell 37% to 156,000 tons, while the average net realized price declined 18% to $363 per ton.
  • Q3 Trio sales volume declined 19% to 22,000 tons, but the average net realized price increased 5% to $353 per ton.
  • Q3 potash production declined 12% to 167,000 tons; langbeinite production increased 14% to 40,000 tons.
  • At September 30, 2013, cash and cash equivalents were $10.4 million, short- and long-term investments totaled $70.5 million, and total cash, cash equivalents and investments were $80.9 million.
  • Long-term debt was $150.0 million, consisting of senior notes issued in April 2013. The $250.0 million revolving credit facility was undrawn and fully available, subject to covenant limitations.
  • Nine-month investing cash outflows were $233.7 million, including $149.4 million for property, plant and equipment and $36.8 million for mineral properties and development costs.
  • Stockholders’ equity was $938.8 million at September 30, 2013, compared with $905.7 million at December 31, 2012.

Material changes versus the prior comparable period

  • Sales declined 45% in Q3 and 23% for the first nine months, primarily because of lower potash volumes and pricing.
  • Potash demand weakened as dealers delayed purchases amid global pricing uncertainty following Uralkali’s withdrawal from the Belarus Potash Corporation marketing arrangement and expectations of additional supply. The later 2013 fall harvest also delayed purchases.
  • Potash per-ton cost of goods sold increased 13% in Q3 to $253, while Trio per-ton cost increased 19% to $322. Lower production at the East and West facilities increased unit costs, and the company recorded a $2.1 million lower-of-cost-or-market inventory adjustment.
  • Nine-month operating cash flow decreased 53% to $62.1 million, reflecting lower earnings and a $39.4 million increase in inventory.
  • Capital spending increased substantially, with $190.1 million invested during the first nine months. The company funded part of the program with $149.3 million of net senior-note proceeds.
  • Total assets increased to $1.18 billion from $994.6 million at year-end 2012, largely reflecting capital investment, inventory growth, and new investments.

Guidance, outlook, commentary, risks and unusual items

  • Management estimated total 2013 capital investment of $245 million to $265 million and expected funding from operating cash flow, existing cash and investments, and senior-note proceeds.
  • The HB Solar Solution mine was expected to begin initial limited production after completion of its processing plant late in 2013, with production ramping through 2014. Expected total project investment was $235 million to $245 million, of which $208.7 million had been invested by September 30.
  • The North compaction facility was nearing completion; two lines were operating and the third was expected to become operational in the first quarter of 2014.
  • West facility recovery projects were expected to be substantially completed in early 2014. East facility results remained exposed to lower-grade, complex ore zones and planned maintenance.
  • Management expected depreciation to continue increasing into early 2014 as major capital projects were completed and placed into service.
  • New Mexico denied certain employment-related tax credits. Intrepid disputed the denial but recorded a reserve of approximately $2.8 million in Q3 for previously claimed credits.
  • The company recorded approximately $1.7 million of income in the first nine months from a New Mexico compensating tax refund and approximately $1.9 million of expense related to settling its pension plan.
  • Asset retirement obligations totaled $21.8 million on a discounted basis and $53.6 million on an undiscounted basis. The company also had $17.3 million of reclamation security, primarily surety bonds.
  • Primary risks include potash and Trio pricing and demand, production disruptions and ore-grade variability, weather affecting solar operations, construction and commissioning execution, transportation and energy costs, environmental and mining regulation, permitting, reserve changes, competition, agricultural conditions, and compliance with debt covenants.

Important facts for investors to verify

  1. Whether potash demand and realized pricing recover after the 2013 market disruption and delayed fall application season.
  2. Progress, final cost, commissioning, and production ramp-up of the HB Solar Solution mine and North compaction facility.
  3. Whether East and West facility recovery and production issues improve without further material inventory adjustments or cost increases.
  4. Liquidity after the unusually heavy capital program, including operating cash generation, investment balances, and availability under the revolving facility.
  5. The outcome of Intrepid’s challenge to the denied New Mexico employment-related tax credits and whether the $2.8 million reserve is sufficient.
  6. Compliance with the senior-note and revolving-credit covenants as earnings and adjusted EBITDA fluctuate.