LINDBLAD EXPEDITIONS HOLDINGS, INC. current report, 02 December 2015

Business Context and Reporting Period

This Form 8-K Current Report was filed by Lindblad Expeditions Holdings, Inc. on December 2, 2015. The filing discloses the entry into material definitive agreements by the Company's subsidiary, Lindblad Expeditions, LLC, regarding the construction of new cruise vessels.

Key Financial Metrics and Agreements

The Company entered into two Vessel Construction Agreements with Nichols Brothers Boat Builders (Ice Floe, LLC) for the construction of two 236-foot, 100-passenger vessels.

  • Total Contract Value: $94.8 million ($48.0 million for the first vessel and $46.8 million for the second).
  • Payment Terms: Monthly payments based on work performed, offset by a previously paid $4.0 million non-refundable slot fee.
  • Delivery Schedule: First vessel due on or before May 1, 2017; second vessel due on or before May 1, 2018.
  • Warranty: One-year warranty capped at $3.0 million in the aggregate for both vessels.

The filing does not provide current revenue, profit, cash flow, margin, debt, or liquidity figures for the reporting period.

Material Changes and Contractual Terms

The primary material change is the commitment to capital expenditures for new fleet expansion. Key contractual provisions include:

  • Risk of Loss: Remains with the Builder until delivery and acceptance by the Company.
  • Liquidated Damages: $15,000 per day for delays exceeding 30 days post-delivery date, capped at $500,000 per vessel.
  • Termination Rights: The Company may terminate if the Builder fails to lay the keel by December 31, 2015, fails to deliver within 180 days of the due date, or becomes insolvent.

Outlook, Risks, and Management Commentary

Management highlighted the strategic expansion of the fleet through these agreements. The press release announcing these terms was issued on December 8, 2015, and is incorporated by reference. The filing notes that the full text of the Agreements will be filed as exhibits to the Annual Report on Form 10-K for the year ended December 31, 2015.

Risks: Potential delays in construction could result in liquidated damages or termination, though the risk of loss during construction is borne by the Builder. The Company's ability to execute depends on the Builder's financial stability and adherence to the keel-laying deadline.

Investor Verification Checklist

  • Verify the status of the $4.0 million non-refundable slot fee previously paid.
  • Confirm the Builder's ability to meet the December 31, 2015, keel-laying deadline to avoid immediate termination rights.
  • Review the full Vessel Construction Agreements in the upcoming Form 10-K for detailed covenants and indemnities.
  • Assess the Company's liquidity position to ensure it can fund the monthly progress payments totaling approximately $90.8 million over the construction period.