Business Context and Reporting Period

This Form 6-K filing by Melco PBL Entertainment (Macau) Limited (MPEL) is dated September 5, 2007. MPEL is a developer and operator of casino gaming and entertainment resort facilities focused exclusively on the Macau market. The filing primarily announces the signing of a new senior secured credit facility by its subsidiary, Melco PBL Gaming (Macau) Limited, to finance the construction of the "City of Dreams" integrated resort.

Key Financial Metrics and Capital Structure

  • Total Credit Facilities: US$1,750,000,000.
  • Term Loan Facility: US$1,500,000,000 with a seven-year maturity, intended to finance the construction of City of Dreams.
  • Revolving Credit Facility: US$250,000,000 with a five-year maturity, available for contingencies and working capital.
  • Shareholder Support: Major shareholders Melco International Development Limited and Publishing & Broadcasting Limited have provided a contingent contribution undertaking of up to US$125,000,000 each (US$250,000,000 aggregate) to cover project contingencies if no other funding is available.
  • Interest Rates: Term Loan bears interest at HIBOR or LIBOR plus a margin.
  • Amortization: Commences 36 months from the signing date.

Material Changes Versus Prior Period

The new US$1.75 billion facility represents a restructuring of a previous US$2.75 billion commitment secured in June 2007. This restructuring was necessitated by adverse changes in credit market conditions in the United States. The new agreement reduces the total committed amount but is deemed sufficient to meet the projected costs for the first phase of the City of Dreams project.

Guidance, Outlook, and Risks

Project Scope and Timeline: The financing covers the first phase of City of Dreams, including a 420,000 sq. ft. casino, 85,000 sq. ft. retail space, the 366-room Hard Rock Hotel, the 295-suite Crown Towers Hotel, the 1,005-room Grand Hyatt Macau, and the 1,700-seat Theatre of Dreams. The project is scheduled to open in 2009.

Future Development: MPEL plans to develop an apartment hotel complex integrated into City of Dreams by the end of 2009, with an estimated cost of US$353 million. The company intends to monitor market conditions to secure additional financing for this phase and for a proposed third hotel casino on the Macau Peninsula.

Risks and Contingencies: The filing highlights risks including the finalization of credit facilities, completion of construction, government regulation, and the ability to raise additional financing. The agreement includes standard covenants regarding EBITDA to interest expense ratios, total indebtedness to EBITDA, and maximum capital expenditure.

Investor Verification Checklist

  • Verify the satisfaction of customary conditions precedent required for the drawdown of the Term Loan Facility.
  • Monitor the company's ability to secure the estimated US$353 million in additional financing for the apartment hotel complex.
  • Track the status of the land concession grant and occupancy permits for the City of Dreams site from the Macau government.
  • Review the impact of the reduced credit facility (from US$2.75 billion to US$1.75 billion) on the project's liquidity buffer.
  • Confirm the activation status of the US$250 million contingent contribution from major shareholders if project funding gaps arise.