Central Puerto S.A. 1Q24 Earnings Summary

Business Context and Reporting Period

Central Puerto S.A. (NYSE: CEPU), Argentina's largest private sector power generator, reported consolidated financial results for the first quarter ended March 31, 2024. The filing was submitted on May 13, 2024. Financial statements are adjusted for inflation under IAS 29 and presented in Argentine Pesos, with U.S. dollar conversions provided for convenience using the official exchange rate (ARS 857.42/USD) as of March 31, 2024.

Key Financial Metrics

  • Revenue: US$150 million (up 15% year-over-year).
  • Adjusted EBITDA: US$84 million (up 11% year-over-year).
  • Net Income: US$32 million (up from US$1 million in 1Q23).
  • Operating Costs: US$59 million (excluding depreciation and amortization).
  • Cash and Equivalents: US$6 million as of March 31, 2024.
  • Other Current Financial Assets: US$100 million.
  • Cash Flow: Net cash used by operating activities was US$18.6 million; net cash provided by investing activities was US$9.3 million; net cash used by financing activities was US$3.7 million.

Material Changes vs. Prior Period

Revenue growth was driven by a 14% increase in Spot/Legacy energy sales and a 16% increase in contract sales, largely due to the consolidation of Central Costanera and the Guañizuil II A solar plant. Operating costs rose 14% due to higher employee compensation and maintenance expenses linked to acquisitions. Net financial results improved significantly, with a loss of US$21 million compared to US$38 million in 1Q23, driven by lower foreign exchange differences on liabilities. The loss on net monetary position decreased by 88% to US$6 million.

Operational generation increased 8% to 5,520 GWh. Thermal generation rose 9% (aided by Central Costanera), while renewable generation increased 26%. Hydro generation from Piedra del Aguila decreased 5% due to lower water availability.

Outlook, Risks, and Unusual Items

Regulatory and Payment Risks: On May 6, 2024, the Secretariat of Energy issued Resolution SE No. 58/2024 regarding delayed payments from CAMMESA for receivables accrued in December 2023, January 2024, and February 2024. Receivables from Dec/Jan are to be paid via Argentine Republic USD bonds (AE38) at face value, while February receivables will be paid in cash. The Company estimates a potential economic loss of approximately ARS 24,450 million (US$29 million) if this mechanism is implemented, excluding default interest.

Strategic Acquisitions: On April 22, 2024, the subsidiary Proener acquired a 4% interest in AbraSilver Resource Corp., owner of the Diablillos silver-gold project in Argentina.

Accounting Impact: Results were affected by a non-cash effect where inflation rates exceeded currency depreciation rates during the quarter, impacting comparability between periods.

Investor Verification Checklist

  • Verify the impact of Resolution SE No. 58/2024 on the valuation of trade receivables and the potential US$29 million economic loss.
  • Confirm the liquidity position given the low cash balance (US$6 million) against debt service obligations.
  • Review the reconciliation of Adjusted EBITDA to Net Income to understand the magnitude of non-cash inflation adjustments.
  • Assess the integration and performance of recently acquired assets (Central Costanera and Guañizuil II A) in future quarters.
  • Monitor the status of CAMMESA payments and the Company's legal or financial measures to preserve rights regarding delayed receivables.