Cheniere Energy Partners, L.P. current report, 04 May 2015

Business Context and Reporting Period

This Form 8-K was filed by Cheniere Energy Partners, L.P. on May 7, 2015, reporting an event dated May 4, 2015. The filing details the entry into a material definitive agreement by Sabine Pass Liquefaction, LLC ("SPL"), an indirect wholly owned subsidiary of Cheniere.

Key Financial Metrics and Contract Terms

The filing discloses a Lump Sum Turnkey Agreement for the Engineering, Procurement, and Construction (EPC) of the Sabine Pass LNG Stage 3 Liquefaction Facility.

  • Contract Price: $2,987,000,000.
  • Counterparty: Bechtel Oil, Gas and Chemicals, Inc. (guaranteed by Bechtel Global Energy, Inc.).
  • Scope: Construction of one liquefaction train with a nominal capacity of approximately 4.5 million tonnes per annum (mtpa).
  • Financial Adjustments: The price is subject to change orders for delays beyond June 30, 2015, changes in law, force majeure, and other specified conditions.

The filing does not provide current revenue, profit, cash flow, margins, debt, or liquidity metrics for the company.

Material Changes and Contractual Provisions

The primary material change is the execution of the EPC contract. Key contractual provisions include:

  • Performance Guarantees: Bechtel must achieve 95% of the performance guarantee to meet minimum acceptance criteria. Failure results in delay liquidated damages and a 10-month correction period.
  • Termination for Convenience: SPL may terminate for convenience. If terminated before the notice to proceed, Bechtel receives $1 million to $2.5 million; if after, up to $30 million, plus costs for work performed.
  • Termination for Delay: If SPL fails to issue a notice to proceed by June 30, 2016, either party may terminate, with Bechtel receiving incurred costs plus a $5 million lump sum.
  • Liability Limits: Bechtel's liability is limited under the contract, except for indemnification obligations, title warranties, and the obligation to complete work to ensure the train is ready to produce LNG.

Outlook, Risks, and Contingencies

Management commentary is limited to the terms of the agreement. Significant risks and contingencies identified in the filing include:

  • Cost Overruns: The contract price is adjustable via change orders for delays, force majeure, or changes in law.
  • Performance Risk: Failure to meet the 95% performance threshold could lead to extended correction periods or default declarations.
  • Force Majeure: Either party may terminate if work is suspended for more than 100 consecutive days or 180 days in aggregate within a 24-month period.
  • Insolvency: Termination rights exist for both parties in the event of insolvency of the counterparty or guarantor.

Investor Verification Checklist

  • Verify the total capital expenditure impact of the $2.987 billion contract on Cheniere's balance sheet and liquidity.
  • Confirm the timeline for the "notice to proceed" to assess the risk of the June 30, 2015, and June 30, 2016, change order and termination triggers.
  • Review the specific daily rates for delay liquidated damages and performance liquidated damages, which are defined in the full contract text (Exhibit 10.1).
  • Assess the financial strength of Bechtel Global Energy, Inc. as the guarantor of the EPC obligations.
  • Monitor for any future filings regarding change orders or delays that could increase the final project cost.