Reporting period: Quarter and nine months ended September 30, 2015; filed November 12, 2015. Centrus supplies low-enriched uranium (LEU) and provides government-funded contract services. It ceased enrichment at Paducah in 2013 and is transitioning to inventory sales, Russian supply purchases, and American Centrifuge development. Fresh-start accounting after emergence from Chapter 11 makes the 2015 Successor and 2014 Predecessor periods not directly comparable.

Financial results and position

MetricQ3 2015Nine months 2015
Revenue$29.2 million, down 76% from $120.7 million$260.3 million, down 33% from $390.5 million
Gross loss$24.4 million; loss margin 83.6%$13.2 million; loss margin 5.1%
Operating loss$50.4 million$71.6 million
Net income (loss)$(55.1) million, versus $418.9 million income in 2014$(85.6) million, versus $340.1 million income in 2014
  • Revenue mix: Q3 LEU revenue was $8.8 million, down 91%; contract-services revenue was $20.4 million. Nine-month LEU revenue was $197.8 million and contract-services revenue was $62.5 million.
  • Cash flow and liquidity: Operating cash use was $45.1 million for the nine months. Cash declined $38.5 million from year-end 2014 to $180.3 million. Working capital was $322.6 million, versus $366.0 million at December 31, 2014. Management said it expected adequate liquidity for at least 12 months.
  • Debt and obligations: Long-term debt was $247.6 million, consisting of 8% PIK Toggle Notes; their estimated fair value was $75.8 million. The notes mature September 30, 2019, subject to potential extension under specified funding conditions. Pension liabilities were $194.2 million and postretirement health and life obligations were $216.3 million. Stockholders’ deficit was $63.9 million.

The prior-year net income included net reorganization gains of $440.0 million in Q3 and $426.9 million for the nine-month period. Current-period results also included a $21.6 million pension remeasurement charge in cost of sales and $3.2 million in SG&A, plus $9.8 million of Q3 workforce-reduction charges. These items and fresh-start accounting affect comparisons.

Changes, outlook, and risks

  • LEU sales volumes fell sharply: SWU revenue declined 91% in Q3 and 56% for the nine-month period. Management attributed the decline to lower deliveries and customer-order timing. The nine-month gross loss improved year over year, but Q3 gross loss widened, primarily reflecting the pension remeasurement charge.
  • DOE funding for American Centrifuge work was expected to fall about 60%, to $35 million annually, with reduced work excluding Piketon cascade operations. The anticipated contract was approximately $2.9 million per month, versus about $6.9 million previously; Centrus cautioned that the final contract and additional Piketon funding were not assured.
  • Centrus recorded $8.7 million of estimated severance charges tied to expected American Centrifuge workforce reductions. It estimated additional Piketon demobilization costs of $10–15 million for Q4 2015 if funding was not restored; further reductions could make restarting operations more difficult.
  • 2015 guidance: Total revenue of $425–450 million, including $350–375 million from SWU and uranium; year-end cash of $175–200 million; and approximately 2 million SWU deliveries. Management also expected approximately 2 million SWU deliveries in 2016. Guidance depended on customer orders, deliveries and purchases, legal outcomes, the ORNL contract, and demobilization costs.
  • Management cited prolonged LEU oversupply and SWU prices at their lowest levels in more than a decade as severe constraints on commercial American Centrifuge economics. Other risks include Russian supply dependence and import or resale restrictions, declining backlog, customer contract actions, and liquidity needs without a credit facility.
  • DOE claims for unpaid contract work totaled approximately $75 million, but the recognized long-term receivable was $19.5 million because collection timing and amount remained uncertain. The PBGC had raised potential pension-related ERISA issues; Centrus disputed the earlier preliminary assessment and said it believed any liability could be satisfied under amended law, but PBGC action remained a contingency.
  • After quarter-end, on October 27, 2015, Centrus signed non-binding principles for a potential modification of its Russian supply agreement; no definitive modification was assured. The Entergy contract dispute was settled through contract modifications, with no monetary payment.

Key facts investors should verify

  • Whether the reduced ORNL contract was finalized and whether funding for Piketon operations was restored; compare resulting revenue, severance, and demobilization costs with management’s estimates.
  • Actual 2015 revenue, SWU deliveries, and year-end cash versus guidance, including the cash effect of Russian LEU purchase obligations.
  • Progress and recoverability of DOE receivables and CDA claims, given the difference between claimed amounts and amounts recognized.
  • Developments in PBGC discussions, pension funding requirements, and the substantial pension and postretirement obligations.
  • Any definitive Russian supply agreement amendment and changes in market prices, customer backlog, or restrictions affecting Russian LEU imports and sales.