This report covers the quarterly period ended June 30, 2002. Cheniere Energy, Inc. is an oil and gas exploration and development company transitioning toward the development of a liquefied natural gas (LNG) receiving terminal in Freeport, Texas. The company operates under the full cost method of accounting for oil and gas properties.
Key Financial Metrics
| Metric | Three Months Ended June 30, 2002 | Six Months Ended June 30, 2002 |
|---|---|---|
| Total Revenues | $37,955 | $199,559 |
| Net Loss | $(2,366,029) | $(4,896,996) |
| Net Loss Per Share (Basic/Diluted) | $(0.18) | $(0.37) |
| Cash and Cash Equivalents | $1,165,259 (as of June 30, 2002) | - |
| Net Cash Used in Operating Activities | - | $(1,698,034) |
| Net Cash Provided by Investing Activities | - | $1,502,575 |
| Total Current Liabilities | $2,775,055 | - |
| Stockholders' Equity | $18,462,073 | - |
Material Changes vs. Prior Period
- Revenue Decline: Oil and gas sales dropped significantly to $37,955 for the quarter (from $774,832 in 2001) and $199,559 for the six months (from $1,746,488 in 2001). This is primarily due to the April 2002 sale of substantially all proved oil and gas reserves (West Cameron Block 49).
- Gain on Sale: The company recognized a gain of $340,257 from the sale of proved properties, offsetting some operating losses.
- Expense Increases: General and Administrative (G&A) expenses increased, driven by $426,678 in additional LNG-related engineering and permitting costs for the quarter.
- Affiliate Losses: Equity in the net loss of the unconsolidated affiliate (Gryphon Exploration Company) increased to $970,938 for the quarter (from $588,889 in 2001). Cheniere's investment basis in Gryphon was reduced to zero, with $2,437,124 of unrecorded losses remaining.
- Debt Activity: The company incurred a $100,544 loss on the early extinguishment of a $500,000 bridge loan. It also secured a $750,000 refundable payment for options on its LNG project, recorded as a note payable.
Outlook, Risks, and Management Commentary
- Liquidity Concerns: Management explicitly states that cash balances and operating cash flows are not adequate to meet future liquidity requirements. There is uncertainty regarding the company's ability to continue as a going concern without additional financing.
- Capital Needs: The company estimates a need for approximately $8,000,000 to fund permitting, environmental, and regulatory work for the LNG terminal in 2002 and 2003.
- Financing Strategy: Future liquidity is expected to be met through the sale of oil and gas interests, sale of seismic data, sale of LNG project participation, or additional equity offerings.
- Future Revenue: Oil and gas revenues are not expected to be significant until late 2003, when new wells (in which Cheniere holds overriding royalty interests) are projected to reach payout.
- Accounting Changes: The company early adopted FAS 145, reclassifying the loss on debt extinguishment as an ordinary loss rather than an extraordinary item.
Investor Verification Checklist
- Verify the status of the $750,000 refundable payment for the LNG project options and the likelihood of exercise by December 15, 2002.
- Confirm the company's progress in securing the $8,000,000 required for LNG permitting and regulatory work.
- Monitor the unrecorded losses of the Gryphon affiliate ($2.4 million) and the potential for further dilution of Cheniere's ownership interest.
- Assess the timeline for the payout of new wells to determine when overriding royalty interests convert to working interests and generate significant revenue.
- Review the terms of the $750,000 note payable secured by company assets, due July 15, 2003, if the LNG options are not exercised.