Power REIT current report, 15 July 2013

Business Context and Reporting Period

This Form 8-K filing by Power REIT, dated July 15, 2013, reports a significant asset acquisition and related financing transaction. On July 12, 2013, the company's wholly-owned subsidiary, PW Tulare Solar, LLC ("PWTS"), acquired approximately 100 acres of land near Fresno, California.

Key Financial Metrics and Transaction Details

  • Acquisition Cost: Approximately $1.6 million, including transaction costs.
  • Asset Description: Land leased to over 20MW of utility-scale solar projects under long-term power purchase agreements with Southern California Edison or Pacific Gas & Electric.
  • Lease Terms: 25-year agreements with annual payments of $157,500 commencing on the project operations date (expected early 2014). Monthly interim payments begin October 1, 2013.
  • Property Taxes: Current annual taxes are approximately $26,500, payable by Power REIT; future increases are the tenant's responsibility.
  • Financing Structure: $1,650,000 in bridge financing secured via A and B notes from Hudson Bay Partners, LP ("HBP"), an affiliate of CEO David H. Lesser.
  • Debt Terms:
    • Blended Yield: 6.35%.
    • Term: 18 months, interest-only with semi-annual payments.
    • A Note: $1,115,000 principal; 5.0% interest for first 6 months, stepping up to 8.5% for the remaining 12 months.
    • B Note: Remaining balance; 9.5% interest for first 6 months, stepping up to 13.5% for the remaining 12 months.
    • Security: First-lien mortgage (deed of trust) and parent guarantee from Power REIT.

Material Changes and Related Party Transactions

The filing discloses a material related-party transaction involving the acquisition of debt from an affiliate of the company's CEO and Chairman. The independent trustees of Power REIT reviewed and approved the loan in a meeting without the CEO present, determining the terms were consistent with third-party financing and in the company's best interest.

Outlook, Management Commentary, and Risks

  • Refinancing Plan: Management intends to refinance the A Note with permanent debt prior to the interest rate step-up. The B Note is expected to be refinanced with debt or equity as soon as practical based on alternative capital costs.
  • Project Timeline: The solar projects are currently under construction and are expected to commence operations in early 2014.
  • Extension Options: Leases include two extension options at fair market rental rates, potentially extending the lease term through 2048.

Investor Verification Checklist

  • Verify the status of the solar project construction and the likelihood of the early 2014 operational start date.
  • Confirm the terms of the power purchase agreements with Southern California Edison and Pacific Gas & Electric.
  • Monitor the company's progress in securing permanent financing to replace the bridge loan before the interest rate step-ups occur.
  • Review the updated investor presentation on the company website for further details on the business plan.