This Current Report on Form 8-K was filed by W&T Offshore, Inc. on October 18, 2021. The filing provides an operational update regarding the impact of Hurricane Ida on the Company's production and announces the timing for the third-quarter 2021 earnings release.
Key Financial and Operational Metrics
- Production Impact: Approximately 80% of production was temporarily shut-in due to Hurricane Ida, resulting in an estimated reduction of 5,500 Boe/d for the third quarter.
- Q3 2021 Production Guidance: Expected to average between 34,200 and 35,100 Boe/d (34% oil, 55% natural gas, 11% natural gas liquids).
- Q4 2021 Production Guidance: Expected to average between 34,800 and 38,500 Boe/d (33% oil, 56% natural gas, 11% natural gas liquids), assuming Big Bend and Dantzler wells return to production by late October.
- October 2021 Production: Averaged approximately 35,900 Boe/d through October 16, 2021.
- Lease Operating Expense (LOE) Guidance: Revised to between $174 million and $180 million for 2021 due to unplanned repair costs, evacuation expenses, and lower-than-anticipated credits.
Material Changes and Unusual Items
The primary material change is the operational disruption caused by Hurricane Ida. While the majority of impacted production was restored in September, the storm incurred unplanned costs for minor repairs and personnel evacuation. Additionally, the Company noted less anticipated Office of Natural Resources Revenue credits and slight increases in base LOE components, leading to the upward revision of the full-year LOE guidance.
Guidance, Outlook, and Risks
The Company expects all hurricane-impacted production to be online by the end of 2021. The third-quarter earnings release is scheduled for November 2, 2021, with a conference call on November 3, 2021. The filing includes standard forward-looking statement disclaimers regarding risks such as oil and gas price volatility, market conditions, reserve estimation uncertainties, and the continued impact of COVID-19.
Investor Verification Checklist
- Verify the actual Q3 2021 production volumes against the 34,200–35,100 Boe/d guidance when earnings are released on November 2, 2021.
- Confirm the return to production of the Big Bend and Dantzler wells by the end of October to validate Q4 guidance.
- Monitor the final 2021 LOE figures to ensure they fall within the revised $174 million–$180 million range.
- Review the upcoming Q3 earnings report for specific details on the financial impact of Hurricane Ida-related costs and credits.