Reporting context: Current report concerning an agreement entered into September 24, 2026. The company announced the agreement in a September 29 press release and signed the filing September 30, 2026. Zone Frontier is developing a West Texas data center campus with HST Technologies, Inc.
Material agreement and key terms
- A subsidiary entered into a ground lease with GKC Operating, LLC for approximately 4,077 acres in Potter County, Texas, surrounding an existing 345 kV substation in the Southwest Power Pool region.
- The company may designate 200–800 acres for data center facilities and at least 1,800 acres for solar generation, battery storage, and related infrastructure. Remaining land may be used for lawful purposes, potentially including natural gas-fired generation.
- The initial term is 30 years from rent commencement, with two 10-year extension options.
- Annual base rent is $6,000 per acre for the data center area and $1,000 per acre for the solar area. Rent starts for each area only when construction begins there. Rent escalates annually based on the five-year rolling average increase in the Consumer Price Index. The lease is absolute triple net.
- The company will pay 0.5% of data center revenue to the landlord; this revenue share ends for acreage the company purchases.
- The company may purchase the data center area for $100,000 per acre before on-site power generation reaches commercial operation, or $135,000 per acre on or after that date. It is not required to purchase other acreage.
- The company may release unneeded acreage on 30 days’ notice, subject to minimum and maximum site-area requirements. If construction has not begun on a site area within 48 months after the effective date, the landlord may terminate the lease and purchase option for that area.
- The lease includes a long-term water supply agreement tied to the lease term. A $250,000 escrow deposit is due upon recording the lease memorandum; it is credited toward a purchase price if the option is exercised. It is refundable if the company terminates before the inspection period ends, except 20% becomes non-refundable if the inspection period is extended.
Financial position and period comparison
This 8-K does not report revenue, profit, cash flow, margins, debt, liquidity, or other company-wide financial results. It provides no comparable-period financial data. Project rent and purchase costs depend on acreage selected, construction timing, and whether the purchase option is exercised.
Conditions, outlook, and risks
- The lease does not commence until conditions precedent are met or waived by the company. These include acceptable title, commitments for at least 200 MW of firm utility service, water supply commitments, an interconnection agreement, required governmental approvals, and satisfactory due diligence.
- The company controls a one-year inspection period, with a possible one-year extension, and may terminate in its sole discretion before that period ends, subject to the deposit terms. The company has guaranteed its subsidiary’s obligations, which are substantially limited until conditions are satisfied or waived and construction begins.
- Management’s stated project rationale is to secure land, water, and development rights for the planned campus while retaining flexibility to secure tenants and financing before rent begins. Development timing, capital commitments, tenant arrangements, and project results remain forward-looking, not guaranteed outcomes.
- Disclosed risks include obtaining tenants, power, grid interconnection, water, permits, and approvals on acceptable terms and timelines; water-right adequacy and enforceability; construction and development risks; market demand and tenant credit risk; and the company’s ability to meet lease obligations or exercise purchase and extension options.
Important facts for investors to verify
- Whether the conditions precedent are satisfied or waived, including the 200 MW power commitment, water commitments, and interconnection agreement.
- Inspection-period status, deposit treatment, and whether the lease has become effective.
- Tenant commitments, financing, construction plans, and actual acreage designated or released.
- Expected project costs and the resulting rent, revenue-share, and purchase-option exposure as development decisions are made.
- The full Ground Lease terms when filed as an exhibit to the company’s Form 10-Q for the quarter in which it was entered into.