This Current Report (Form 8-K) was filed on October 13, 2021, by Allegiant Travel Company. The filing details a material definitive agreement entered into by Sunseeker Florida, Inc. (SFI), a wholly-owned subsidiary of the Company, to secure financing for the Sunseeker Resorts at Charlotte Harbor project.
Key Financial Metrics and Obligations
The filing discloses the creation of a new direct financial obligation with the following terms:
- Total Loan Amount: Up to $350,000,000.
- Lender: Entities managed by Castlelake, L.P.
- Interest Rate: 5.75% per annum, payable semi-annually.
- Maturity Date: October 2028.
- Principal Repayment: Semi-annual payments of $26,000,000 beginning in 2025.
- Collateral: The loan is secured by the Project and all shares of SFI.
- Guarantees: Allegiant Travel Company has guaranteed the full amount of the debt and the completion of the Project.
Material Changes and Funding Schedule
The Company expects the following disbursement schedule for the loan proceeds:
- Initial Tranche: $175,000,000 expected to be advanced before the end of October 2021.
- Subsequent Tranches: The remaining balance is scheduled to be advanced in two tranches in April 2022 and October 2022.
The proceeds are designated specifically to fund the remaining construction of the initial phases of the Sunseeker Resorts at Charlotte Harbor.
Outlook, Risks, and Covenants
The Credit Agreement includes covenants similar to those in the Company's existing Term Loan B. The agreement contains various events of default; upon such an event, the Lender may cease funding obligations and demand immediate payment of all outstanding amounts, subject to customary cure rights. The filing does not provide specific revenue, profit, or cash flow metrics for the reporting period, as this is a transaction-specific report.
Key Facts for Investor Verification
- Verify the impact of the new $350 million debt obligation on the Company's overall leverage ratios and liquidity position.
- Confirm the status of the Sunseeker Resorts at Charlotte Harbor construction project and the necessity of the remaining funding tranches.
- Review the specific covenants in the Credit Agreement to understand potential restrictions on future operations or additional debt.
- Monitor the Company's ability to meet the semi-annual principal payments starting in 2025.