Purecycle Technologies, Inc. current report, 25 October 2023

PureCycle Technologies, Inc. — Form 8-K Summary

Report date: October 25, 2023. The filing reports developments concerning the revenue bonds financing PureCycle’s Ironton, Ohio recycling facility and a proposed second waiver of related covenant defaults.

Business Context and Reporting Period

PureCycle Ohio LLC, an indirect wholly owned subsidiary, borrowed proceeds from revenue bonds issued by the Southern Ohio Port Authority to acquire, construct, and equip the Ironton Facility. The facility was required to be completed by December 1, 2022, but completion was delayed by construction and operating challenges, including impacts associated with COVID-19, the Russia-Ukraine conflict, and severe weather.

The filing covers events through October 25, 2023, including a proposed Limited Waiver and Second Supplemental Indenture agreed to in principle by the majority holders of the Series 2020A Bonds.

Financial Metrics, Debt, and Liquidity

  • PureCycle’s financing includes outstanding Series 2020A revenue bonds; the filing does not provide the bonds’ outstanding principal balance, interest rate, or current carrying value.
  • PureCycle Ohio LLC must deposit an additional $50 million into the Trustee Account, resulting in an Aggregate Trustee Deposit of at least $100 million while any bonds remain outstanding.
  • If no default or event of default is continuing and specified conditions are met, $50 million may be released back to PureCycle Ohio LLC.
  • Investment income or earnings on amounts held in the Trustee Account and Liquidity Reserve Escrow Fund may be released quarterly, subject to compliance with the waiver and the absence of defaults.
  • If a milestone is missed, the company must pay interest at the Default Rate from the applicable milestone date until satisfaction, and access to specified trust and escrow funds will be restricted during the applicable cure period.
  • The filing does not provide revenue, profit, cash flow, margin, or other operating financial results for the period.

Material Changes Versus the Prior Comparable Period

  • The company was unable to achieve the prior requirement to produce 4.45 million pounds of pellets in a single month by September 30, 2023, resulting in a September Milestone Event of Default.
  • The shortfall followed a full plant power outage on August 7, 2023, and a key seal system failure on September 3, 2023, which halted operations while damage and root cause were assessed.
  • On September 13, 2023, PureCycle Ohio LLC issued a Force Majeure Notice, which the Trustee disputed. Under the proposed second waiver, the notice will be expressly withdrawn.
  • Subject to execution of definitive documents, the bondholders agreed in principle to waive the September Milestone Event of Default and replace prior milestones with revised deadlines.

Guidance, Outlook, Risks, and Unusual Items

  • Produce 4.45 million pounds of pellets from feedstock for 30 consecutive days by December 31, 2023.
  • Complete performance testing by February 28, 2024.
  • Complete the Ironton Facility project by March 31, 2024.
  • Produce 8.90 million pounds of pellets from feedstock for 30 consecutive days by April 30, 2024.
  • Reach fully ramped production of 107 million pounds per year from project feedstock by April 30, 2024.
  • A missed milestone would not become an event of default until 90 days after the applicable milestone date, but default-rate interest would accrue during the cure period and access to specified funds would be blocked.
  • The second waiver remained subject to further negotiation and execution by the parties as of the filing date; its final terms were not yet definitive.
  • Key risks include additional plant failures, commissioning delays, inability to achieve production targets, liquidity constraints from the required deposit and escrow restrictions, and potential bondholder remedies if defaults are not cured.

Important Facts for Investors to Verify

  • Whether the Second Limited Waiver was finalized and executed, and its final terms.
  • Whether the additional $50 million Trustee Account Deposit was funded and the required $100 million aggregate balance was maintained.
  • Whether the Ironton Facility met each production, performance-testing, completion, and ramp-up milestone.
  • The outstanding principal balance, maturity, interest rate, and default-rate provisions of the Series 2020A Bonds.
  • The company’s available unrestricted cash, liquidity sources, and access to escrowed funds during any milestone cure period.
  • Whether further plant outages, equipment failures, or construction issues affected commissioning or commercial production.