Financial and operating results

MetricFY 2011FY 2010
Metal concentrate sales$105.2 million$14.8 million
Mine gross profit$87.2 million$9.8 million
Mine gross margin82.9%66.4%
Operating income (loss)$45.7 million$(22.8) million
Net income (loss)$58.4 million$(23.1) million
Diluted earnings (loss) per share$1.03$(0.46)
Net cash from (used in) operating activities$42.4 million$(21.3) million

Revenue rose substantially as 2011 included a full production year and higher realized prices: average realized gold was $1,596/oz versus $1,201, and silver was $35/oz versus $20. Production totaled 66,159 gold-equivalent ounces at a reported non-GAAP cash cost of $136 per ounce, net of by-product credits. The company milled 214,215 tonnes. Its La Arista underground mine supplied most production from March onward.

Fourth-quarter 2011 sales were $35.4 million and mine gross profit was $30.0 million, compared with $4.8 million and $2.7 million, respectively, in fourth-quarter 2010. Fourth-quarter net income was $38.0 million; the filing attributes the annual tax benefit principally to a fourth-quarter reduction in deferred-tax valuation allowances.

Financial position and capital allocation

  • At year-end, cash and cash equivalents were $52.0 million, total current assets $89.5 million, current liabilities $30.2 million, working capital $59.3 million, and shareholders’ equity $87.1 million.
  • The company reported no outstanding debt. Total liabilities were $32.5 million, including a $2.3 million asset-retirement obligation.
  • 2011 cash flows included $9.3 million used in investing and $28.4 million used in financing. Financing outflows chiefly reflected $26.5 million of dividends declared and $2.0 million of share repurchases.
  • The company declared $0.50 per share in dividends during 2011 and began a regular $0.05 monthly dividend in August. Dividends were classified as return of capital; future payments remain at the board’s discretion.
  • The board authorized a $20 million repurchase program; 104,251 shares were repurchased for approximately $2.0 million by year-end. The company also bought $3.0 million of physical gold and silver bullion.

Changes, outlook, and notable items

  • Gold Resource moved from losses in 2010 and 2009 to reported 2011 profitability. The improvement reflects higher sales and margins, but also a $12.0 million income-tax benefit, including a $28.3 million valuation-allowance reduction, and $2.7 million of currency-exchange gains.
  • An unusual April 2011 storm flooded lower levels of the La Arista mine and damaged site infrastructure. The company reported a $2.5 million loss, or $1.8 million net of tax, and said mining was affected for approximately two months.
  • Management targeted 2012 production of 120,000–140,000 gold-equivalent ounces, expecting more stopes and working faces. It budgeted approximately $8.0 million for 2012 exploration, including $4.8 million at El Aguila; these are plans, not assured results.
  • The mill’s agitated-leach circuit had not been used; processing was through the flotation circuit. The company planned continued underground development and mill optimization.
  • The company had no proven or probable reserves at any property and had not completed a feasibility study. It remained an SEC-defined exploration-stage company and expensed substantially all exploration and mine-development costs as incurred.

Risks and contingencies

Operations depended on a single producing project and mine, with exposure to mine interruptions, geology and recovery, metal prices, Mexican peso movements, permitting and environmental requirements, community and surface-access arrangements, and political or security conditions in Oaxaca. The company did not hedge metal production. Sales were highly concentrated: 96% of 2011 concentrate sales went to Consorcio and 4% to Beheer, both Trafigura Group companies. The filing reported no material legal proceedings and no off-balance-sheet arrangements. Management and the auditor concluded internal control over financial reporting was effective at year-end.

Important facts for investors to verify

  • Whether La Arista can sustain production and achieve the 2012 target despite the 2011 flood disruption and the project’s lack of proven or probable reserves.
  • Whether reported earnings and cash generation are repeatable without the valuation-allowance release, favorable currency gains, or elevated metal prices.
  • Actual cash costs, recoveries, mine-development spending, and the reconciliation of the reported non-GAAP cash-cost measure to GAAP costs.
  • Customer concentration, provisional concentrate pricing exposure, and the company’s ability to maintain alternative buyers and timely collections.