NIOCORP DEVELOPMENTS LTD annual report, FY2023

NioCorp Developments Ltd. — Form 10-K Summary

Reporting period: Fiscal year ended June 30, 2023 (not calendar-year 2022 Q4). U.S. dollars unless noted. NioCorp is a development-stage mineral company advancing the Elk Creek project in Nebraska; it had no mining revenue or commercial production.

Business context and project

Elk Creek is planned as an underground mine producing niobium, scandium and titanium, with rare-earth oxides under evaluation. During FY2023, NioCorp completed and operated a demonstration plant, completed initial site preparation and geotechnical work, and reported improved demonstrated recoveries. Construction has not begun and depends on financing, permits, detailed engineering and board approval.

Financial performance and liquidity

MetricFY2023 / June 30, 2023Comparable period
Mining revenueNoneNone in FY2022
Operating expenses$37.4 million$7.8 million in FY2022
Net loss attributable to NioCorp$40.1 million; $1.34 per share$10.9 million; $0.41 per share in FY2022
Cash used in operating activities$17.3 million$6.2 million in FY2022
Cash and cash equivalents$2.3 million$5.3 million at June 30, 2022
Working capital$0.2 million$0.6 million at June 30, 2022
Total assets / total liabilities$20.9 million / $29.8 million$22.8 million / $5.1 million at June 30, 2022

Margins are not meaningful because there was no operating revenue. The FY2023 loss increase primarily reflected GXII transaction-related costs and fair-value accounting, as well as higher professional and exploration expenses. Transaction-related losses were reported at $23.8 million, including $13.2 million initial fair value for earnout shares and $3.0 million for private warrants; these are not all cash expenses.

At year-end, convertible debt had a $10.6 million carrying value on the balance sheet and $13.0 million remaining principal. The unsecured Yorkville debentures bear 5% simple interest, mature September 17, 2024 (with a possible six-month extension in specified circumstances), and may convert into shares subject to contractual limits. NioCorp reported no related-party loan outstanding at year-end.

Management estimates planned cash needs of approximately $11.8 million through June 30, 2024 and says available cash was insufficient to fund basic operations for the following 12 months. It estimated an additional $8–9 million, net of subsequent September financing, would likely be needed to advance financing, permitting and engineering work. The auditor issued an unmodified opinion on the financial statements but highlighted substantial doubt about the company’s ability to continue as a going concern.

Material changes and project economics

  • Loss attributable to NioCorp rose to $40.1 million from $10.9 million in FY2022; operating cash use increased to $17.3 million from $6.2 million.
  • The March 2023 GXII business combination brought NioCorp’s Nasdaq listing and new financing, but the company reported only $2.2 million of net cash from GXII after transaction costs and assumed net liabilities. The transaction also created warrant and earnout liabilities and substantial potential share dilution.
  • The $65 million Yorkville equity facility runs for up to three years, subject to conditions and limits; shares are sold at 97% of the applicable market price. It is not assured that NioCorp can draw the full amount. NioCorp reported approximately $62.6 million of potential net proceeds under the facility, subject to availability and terms.
  • The 2022 feasibility study, incorporated by reference, projected a 38-year mine life, 2,764 tonnes per day, and initial capital costs of about $1.14 billion including contingency; total initial and sustaining capital was estimated at about $1.56 billion, excluding roughly $44 million for closure and reclamation. These are study estimates, not committed spending or current operating results.
  • The study’s projected economics use first-quarter 2019 constant dollars and assumed commercial production in 2025, conditional on financing and other prerequisites. The filing does not establish this as current management guidance.
  • Mineral reserves and resources were unchanged from June 30, 2022. The reported probable reserve is 36.656 million tonnes; no proven reserve is reported. Rare-earth resources are reported, but the filing says further technical and economic work is required and no rare-earth reserve has been established.
  • Demonstration-plant testing indicated niobium recovery of 90.7% through hydrometallurgy and expected 86.7% overall ferroniobium recovery, versus prior reported process figures of 86.8% and 82.4%. Titanium recovery to final product was reported at 83.7%, versus 40.3% previously; the company is still evaluating the cost of producing titanium tetrachloride instead of the study’s titanium dioxide product. These test results have not yet demonstrated commercial-scale performance or updated project economics.

Outlook, risks and unusual items

NioCorp applied to the Export-Import Bank of the United States for project debt financing under its “Make More in America” initiative. The application remained subject to due diligence, final terms and definitive documents; no final commitment was disclosed. September 2023 financing raised $1.0 million gross in a private placement and $0.5 million gross through Yorkville share sales, after the fiscal year-end.

  • Funding and dilution: Continued operations and project development depend on raising additional capital. Equity-line availability, warrant exercises and EXIM financing are uncertain. The convertible debt, warrants, exchangeable shares and future equity issuances could materially dilute existing shareholders.
  • Execution and economics: The project requires major financing, engineering, procurement, construction and commissioning. Inflation, labor and supply-chain costs, commodity prices, customer demand and the ability to secure remaining offtake agreements may affect feasibility.
  • Permits, water and environmental obligations: The company reports key construction permits, including a Nebraska air permit and county special-use permit, but additional operating permits remain necessary, including a solid-waste permit, air operating permit and radioactive materials license. Water treatment, zero-process-liquid-discharge plans and waste management introduce execution and permitting risks.
  • Controls and reporting: Management concluded disclosure controls and internal control over financial reporting were ineffective at June 30, 2023 because of material weaknesses involving non-routine transaction accounting, control environment, risk assessment, control activities and monitoring. The filing describes prior-period restatements and an immaterial FY2023 quarterly revision related to warrant valuation; remediation was ongoing.
  • Other considerations: The company has a history of losses, no recurring operating revenue, limited insurance for mining risks, and exposure to commodity and currency fluctuations. It also says it may be a passive foreign investment company for U.S. tax purposes.

Key investor verification points

  • Confirm current cash runway, liabilities and financing raised after June 30, 2023, and whether further funding has been secured on acceptable terms.
  • Check the status and conditions of the Yorkville equity facility, EXIM application, and Yorkville debentures, including repayment, conversion and potential share dilution.
  • Verify updated project capital costs, schedule and economic analysis incorporating demonstration-plant results, titanium tetrachloride plans and any rare-earth additions.
  • Track remaining permits, water-treatment and waste-management approvals, and whether design changes require additional federal permits.
  • Review progress on internal-control remediation and the implications of prior restatements and the disclosed warrant-valuation revision.
  • Assess the assumptions and uncertainty behind mineral reserves, resource estimates, product prices, recoveries and offtake arrangements; resources are not reserves and do not by themselves establish economic viability.