Business context and reporting period
Agencia Comercial Spirits Ltd. filed this Form 6-K for November 2026. On November 13, its Indonesian subsidiary entered into two contracts for mechanical, electrical and plumbing equipment supply and installation for Phase 1B of the planned AGCC-JKT01 data center in West Java. The company announced the contracts on November 19.
Financial and operating information
- Contract value: Aggregate fixed lump-sum price of US$60 million to US$65 million, excluding Indonesian VAT. Prices are denominated in U.S. dollars but payable in Indonesian rupiah at the Bank Indonesia middle rate on each invoice date. Prices may be adjusted for specified events, including instructed variations.
- Cash flow and revenue: The contracts concern construction and do not directly generate revenue. The filing provides no project cash-flow forecast or expected revenue, profit, or return.
- Other metrics: The filing provides no financial statements or figures for revenue, profit, margins, cash flow, debt, or liquidity.
Changes and outlook
The Phase 1B contracts follow letters of award for Phase 1A MEP works announced September 1, 2026. Equipment delivery and installation are scheduled to be completed in 2027, subject to contractual milestones. The filing does not provide a comparable-period financial performance analysis.
Risks and contingencies
The contracts include capped liquidated damages for delays, a post-taking-over defects notification period, and termination-for-convenience rights for the subsidiary, subject to payment for work performed and reasonable costs incurred. Phase 1B completion and data center operations remain dependent on contractor performance, related construction and power supply works, funding availability, and regulatory approvals. The company gives no assurance of completion, operational capacity, customer utilization, revenue, profitability, or positive cash flow. The filing also cautions that forward-looking statements rely on assumptions subject to significant uncertainties and contingencies.
Key facts for investors to verify
- Final contract costs, including VAT, variations, and any currency-exchange effects on rupiah payments.
- Funding availability and the company’s ability to meet construction-related obligations.
- Progress against 2027 milestones, including contractor performance and related power supply and construction work.
- Regulatory approvals, operational capacity, customer utilization, and eventual project economics.