Business Context and Reporting Period
This Current Report on Form 8-K was filed by Exelon Corporation and Exelon Generation Company, LLC on November 18, 2016. The filing reports the entry into material definitive agreements involving subsidiaries of Constellation Energy Nuclear Group, LLC (CENG) and Entergy Corporation with the New York State Energy Research & Development Authority (NYSERDA).
Key Financial Metrics and Agreement Terms
The filing details three separate agreements for the procurement of Zero Emission Credits (ZECs) under the New York Clean Energy Standard. Key terms include:
- Term: April 1, 2017, through March 31, 2029.
- Structure: ZECs will be procured in six, two-year tranches.
- Pricing Mechanism: Administratively determined based on the USIWG Social Cost of Carbon (escalating) less a fixed baseline of $10.41/short ton.
- Tranche 1 Price: $17.48 per MWh.
- Volume Cap: Capped at the verifiable historic contribution of the facility to the clean energy resource mix.
- Cost Recovery: Incorporated into commodity charges on customer bills via Load Serving Entities.
The filing does not provide specific revenue, profit, cash flow, margin, debt, or liquidity figures for the reporting period.
Material Changes
The primary material change is the execution of the NYSERDA Agreements, which establish a new revenue stream for the nuclear facilities (Nine Mile Point Nuclear Station and R. E. Ginna Nuclear Power Plant) to preserve their environmental attributes. No other material changes to financial condition or operations are detailed in this specific report.
Outlook, Risks, and Contingencies
The report contains forward-looking statements subject to risks and uncertainties. Management directs investors to risk factors and MD&A sections in Exelon's 2015 Form 10-K, Pepco Holdings' 2015 Form 10-K, and Exelon's Q3 2016 Form 10-Q for a comprehensive list of factors that could cause actual results to differ. The company explicitly states it does not undertake any obligation to publicly release revisions to these forward-looking statements.
Investor Verification Checklist
- Verify the full text of the ZEC Standard Contracts (Exhibits 10.1 and 10.2) for complete terms and conditions.
- Confirm the specific historic contribution volumes for Nine Mile Point and R. E. Ginna to estimate total potential ZEC revenue.
- Review the referenced 2015 10-K and Q3 2016 10-Q filings for detailed risk factors regarding nuclear operations and regulatory changes.
- Monitor future administrative determinations of the Social Cost of Carbon to assess pricing escalations for subsequent tranches.