This Form 6-K filing by BHP Group Limited, dated July 11, 2024, announces a strategic decision regarding its Western Australia Nickel operations (including Nickel West and the West Musgrave project). The filing details the temporary suspension of these operations effective October 2024 due to global nickel market oversupply and declining forward consensus prices.
Key Financial Metrics and Impacts
- Impairment Charges: BHP expects to recognize an additional non-cash impairment charge of US$0.3 billion (AU$0.45 billion) pre-tax as an exceptional item in FY2024. This follows a previous non-cash impairment of approximately US$3.5 billion announced in February 2024.
- Operating Loss: Western Australia Nickel is expected to report an underlying EBITDA loss of approximately US$300 million for the financial year ending June 30, 2024.
- Historical Cash Flow: The division has recorded negative cash flow every year since FY2020.
- Capital Investment: Since FY2020, BHP has invested approximately US$3 billion (AU$4.4 billion) to sustain the business and reorient production for the battery and electric vehicle market.
- Maintenance Costs: During the suspension, BHP will invest approximately US$300 million (AU$450 million) per annum to support a potential re-start.
- Community Support: A AU$20 million Community Fund has been established to support local communities.
Material Changes and Operational Status
Operations at the Kwinana nickel refinery, Kalgoorlie nickel smelter, Mt Keith and Leinster operations, and the West Musgrave project will be suspended starting October 2024. A transition period commenced in July 2024, with handover activities for suspension completing by December 2024. The decision follows a review initiated in February 2024 and is driven by strong growth in alternative low-cost nickel supply globally.
Outlook, Management Commentary, and Risks
- Review Timeline: BHP intends to review the decision to temporarily suspend operations by February 2027.
- Workforce Strategy: Frontline employees will be offered alternative roles within BHP or the choice of redundancy. Redundancy payments and contractual costs will be recognized in HY2025 Financial Statements.
- Future Investment: BHP remains committed to Western Australia, with expected investment in the state exceeding AU$12 billion over the next five years.
- Risks: The primary risk cited is the substantial economic challenge driven by global nickel oversupply, which has prevented the business from overcoming losses despite significant capital investment.
Key Facts for Investor Verification
- Verify the timing and magnitude of the additional US$0.3 billion impairment charge in the upcoming FY2024 full-year results.
- Monitor the execution of the transition period and the commencement of the care and maintenance program in October 2024.
- Track the recognition of redundancy and contractual costs in the HY2025 financial statements.
- Assess the impact of the suspension on BHP's overall nickel production guidance and downstream battery supply chain strategy.
- Confirm the status of the AU$20 million Community Fund and its deployment to local stakeholders.