Cheniere Energy Partners, L.P. current report, 31 July 2012

Business Context and Reporting Period

This Form 8-K filing by Cheniere Energy Partners, L.P. (the "Partnership") reports material events occurring on July 31, 2012. The filing details the closing of a major project financing facility, the execution of definitive agreements regarding investor rights and terminal usage, and the unregistered sale of equity securities. The primary focus is the development of liquefaction facilities at the Sabine Pass LNG terminal in Cameron Parish, Louisiana.

Key Financial Metrics and Agreements

  • Debt Financing: Sabine Pass Liquefaction, LLC ("SPL") closed a $3.6 billion senior secured credit facility (Term Loan A) to fund two LNG trains with a nominal capacity of at least 182.5 million MMBtu per year each.
  • Equity Transaction: Cheniere Class B Units Holdings, LLC ("CBUH") acquired 22,222,223 Class B Units from the Partnership for $333.3 million.
  • Terminal Capacity: Under the Amended Terminal Use Agreement, SPL reserved 781,830,000 MMBtu of annual LNG delivery/receipt capacity (approx. 2.0 billion cubic feet per day).
  • Interest Rates: LIBOR loans bear interest at LIBOR plus 3.50% (pre-completion) or 3.75% (post-completion). Base rate loans bear interest at Prime plus 2.50% (pre-completion) or 2.75% (post-completion).
  • Fees: Upfront fees to agents and lenders total approximately $178 million.
  • Liquidity and Cash Flow: The filing does not provide specific cash flow, revenue, or profit metrics for the Partnership as this is a current report on specific events rather than a periodic financial statement.

Material Changes and Agreements

Investors' and Registration Rights Agreement

The Partnership, Cheniere Energy, Inc., and Blackstone CQP Holdco LP entered into an agreement providing registration rights for Common Units held by investors. A two-year lock-up period applies to the transfer of Class B Units and converted Common Units. Blackstone retains the right to appoint a director nominee to Cheniere's board while holding significant equity interests.

Terminal Use Agreement

SPL and Sabine Pass LNG, L.P. ("SPLNG") executed a Second Amended and Restated Terminal Use Agreement. The term is 20 years with up to eight five-year extensions. SPL is obligated to pay fixed monthly reservation and operating fees, plus a 2% retainage on LNG delivered. The Partnership provided an irrevocable guaranty for SPL's obligations under this agreement.

Credit Facility Conditions

The $3.6 billion facility is subject to strict conditions precedent for advances:

  • Initial Advance: Requires receipt of at least $890 million in equity/subordinated debt and a Department of Energy "finding of no significant impact."
  • Second Advance: Requires receipt of at least $1.89 billion in equity/subordinated debt, expenditure of $1.79 billion on project costs, and repayment/refinancing of specific senior notes.

Financial Covenants

  • Debt Service Coverage Ratio (DSCR): Post-completion, SPL must maintain a minimum DSCR of 1.15x. A cure mechanism exists if the ratio is between 1.00x and 1.15x.
  • Distribution Restrictions: Equity distributions are restricted prior to project completion. Post-completion distributions require a DSCR of at least 1.25x.
  • Debt to Equity: Additional replacement debt is permitted only if the debt-to-equity ratio does not exceed 65:35.

Outlook, Risks, and Contingencies

  • Project Completion Risk: Failure to complete the project within the specified timeframe or meet commercial delivery deadlines constitutes an event of default.
  • Regulatory Risk: Advances are contingent on governmental approvals, including the Department of Energy export authorization.
  • Force Majeure: SPL may terminate the Terminal Use Agreement if SPLNG declares force majeure extending beyond 18 months or fails to meet specific delivery volume thresholds.
  • Interest Rate Protection: SPL is required to maintain interest rate protection agreements covering at least 75% of its senior secured debt.

Investor Verification Checklist

  • Verify the status of the Department of Energy "finding of no significant impact" required for the initial loan advance.
  • Confirm the receipt of the required $890 million in equity/subordinated debt proceeds to trigger the first loan tranche.
  • Review the full text of the Credit Agreement (Exhibit 10.4) for specific definitions of "Project Completion Date" and default triggers.
  • Monitor the repayment status of Cheniere's convertible senior notes (due August 2012) and SPLNG's senior secured notes (due November 2013), as these are conditions for the second loan advance.
  • Assess the impact of the 2-year lock-up period on the liquidity of Class B Units and Common Units held by Blackstone and affiliates.