Halliburton Company — Q1 2006 8-K Summary
Filing and period: Filed April 20, 2006 under Item 2.02; reports unaudited results for the three months ended March 31, 2006, compared primarily with Q1 2005. The company operates through Energy Services Group (ESG) and KBR.
Financial results
| Metric | Q1 2006 | Q1 2005 | Change |
|---|---|---|---|
| Revenue | $5.210 billion | $4.783 billion | Up 9% |
| Operating income | $755 million | $575 million | Up 31% |
| Income from continuing operations | $481 million; $0.90 diluted EPS | $359 million; $0.71 diluted EPS | Up 34% by income |
| Net income | $488 million; $0.91 diluted EPS | $365 million; $0.72 diluted EPS | Up 34% by income |
| Capital expenditures | $160 million | $142 million | Up $18 million |
Q1 2006 net income included $7 million after tax from discontinued operations; Q1 2005 included $6 million. The statements reclassify KBR Production Services as discontinued operations. Depreciation, depletion and amortization was $128 million. The filing provides selected capital spending information, but does not provide operating cash flow or free cash flow.
Segments, margins and material changes
- ESG: Revenue was $2.938 billion, up 35%; operating income was $727 million, up 42%. Operating margin was 24.7%, versus approximately 23.5% a year earlier, calculated from reported segment revenue and operating income. Growth reflected increased activity, asset utilization and pricing, particularly in North America. ESG revenue rose across all reported geographic regions.
- KBR: Revenue was $2.272 billion, down 13%; operating income was $62 million, down 34%. Government and Infrastructure operating income fell 62% to $20 million, principally reflecting reduced LogCAP III activity and period-to-period differences in award fees and settlements. Energy and Chemicals operating income was $42 million.
- Iraq-related work: Contributed approximately $1.1 billion in revenue and $27 million of operating income, a 2.5% margin before corporate expenses and taxes.
- Backlog: Total reported backlog was $9.454 billion at March 31, versus $10.795 billion at December 31, 2005. Firm orders were $8.980 billion; government orders firm but not yet funded, letters of intent and unsigned awards were $474 million. Production Services backlog, excluded from continuing-operations backlog, was $1.1 billion.
Liquidity, debt and balance sheet
At March 31, 2006, cash and equivalents were $2.278 billion and current assets were $9.739 billion, against current liabilities of $4.162 billion. Long-term debt was $2.793 billion and current debt maturities were $360 million, for total reported debt of $3.153 billion. Total liabilities were $8.147 billion and shareholders’ equity was $6.872 billion. Compared with December 31, cash decreased $113 million, current liabilities decreased $265 million, and total debt decreased $21 million. The filing does not provide a cash flow statement sufficient to explain these movements.
Outlook, commentary, risks and unusual items
- Management described ESG as having another record quarter and cited customer spending strength in North America and growth from Eastern Hemisphere investment. No formal earnings or revenue guidance was provided.
- KBR Production Services was expected to be sold in Q2 2006; management anticipated an approximately $100 million pretax gain. Halliburton also cited KBR’s Form S-1 filing as a milestone in its strategy to separate KBR from ESG.
- Q1 unusual items included a $30 million impairment charge and loss on an Australian railroad equity investment, attributed to project and mining delays, and a $15 million Barracuda-Caratinga project charge for completion costs and warranty matters. These reduced reported KBR operating income.
- Petrobras and KBR agreed on technical and operational acceptance of completed floating production vessels; final lender approval was expected shortly, later than previously anticipated.
- The release’s forward-looking-statement risks include government audits and investigations, contract disputes, political and security conditions, weather, customer spending and oil and gas demand, fixed-fee project performance, regulation, taxes, competition, raw material availability, joint ventures and planned dispositions. The company disclaimed an obligation to update forward-looking statements.
- New awards and project developments included a two-year $40 million Oman services contract, a three-year Russia services contract, a £8 billion UK defense-related joint venture contract (including a £3.2 billion 35-year services package and £1.2 billion nine-year construction program), and financial close on an approximately $400 million ammonia-plant project in Egypt. Award values and contract structures should not be treated as equivalent to near-term revenue.
Important facts for investors to verify
- Whether the expected Q2 Production Services sale closed and whether the anticipated approximately $100 million pretax gain was realized.
- How KBR’s separation progressed, and the subsequent status, funding, and execution of its government and infrastructure backlog.
- Whether the Australian railroad investment delays and Barracuda-Caratinga project costs resulted in further charges or cash requirements.
- The conversion and timing of reported backlog, especially unfunded government orders and awards not yet signed.
- Operating cash flow, working-capital movements and capital spending needs; operating cash flow is not reported in this filing.
- Exposure to Iraq-related work and the sustainability of ESG pricing, utilization and regional growth.