Reporting period: Three months ended March 31, 2024. Financial statements are unaudited; amounts below are in U.S. dollars. The company explores for critical metals, principally copper, and also operates data-processing and vanadium-flow battery businesses. Its mining projects are at the exploration stage and generated no revenue.
Financial performance and position
| Metric | Q1 2024 | Q1 2023 / prior period |
|---|---|---|
| Revenue | $0.36 million | $0.68 million |
| Gross profit | $0.26 million | $0.50 million |
| Operating expenses | $57.1 million | $39.1 million |
| Net loss | $60.1 million | $38.6 million |
| Net loss attributable to common stockholders | $55.5 million; $0.46 per share | $36.1 million; $0.39 per share |
| Cash used in operating activities | $50.0 million | $30.0 million |
| Cash and cash equivalents | $179.4 million | $205.0 million at December 31, 2023 |
| Working capital | $152.6 million | $176.8 million at December 31, 2023 |
| Total assets / liabilities | $461.2 million / $111.4 million | $487.2 million / $110.9 million at December 31, 2023 |
Revenue was entirely from data-processing services; no software-licensing or energy-storage revenue was reported. Exploration expense rose to $43.6 million from $26.6 million, led by Santa Cruz ($27.8 million), Tintic ($3.5 million), San Matias ($3.5 million) and Hog Heaven ($3.3 million). General and administrative expense increased to $12.6 million from $10.6 million, partly reflecting $1.8 million in short-term cash bonuses. Share of losses from equity-method investees increased to $3.0 million, including $2.1 million from the Ma’aden joint venture.
Debt included a $50.1 million secured note payable, of which $13.8 million was current, and $29.0 million of VRB convertible debt. The secured note bears interest at prime plus 1%; scheduled principal installments are $12.1 million annually, beginning in November 2024. VRB’s bond accrues interest at 8% and matures in 2026, with conversion provisions or repayment if no qualifying event occurs. Cash of $30.2 million was held by non-wholly-owned subsidiaries and was not available for general corporate purposes.
Material developments and outlook
- Common-stockholder net loss increased $19.4 million year over year, mainly due to higher exploration spending, higher general and administrative costs, greater equity-method losses, and lower revenue. Loss per share increased despite the larger weighted-average share count.
- Operating cash use increased by $19.9 million year over year. Management attributed Q1 2024 operating cash use primarily to $43.0 million of cash exploration expenditures and $9.9 million of cash general and administrative costs. Cash fell $25.7 million during the quarter.
- On March 11, the company acquired control of Sama Nickel Corporation and began consolidating it after completing its earn-in for a 60% interest in the Samapleu-Grata project. On February 6, it acquired the remaining Kaizen shares, making Kaizen wholly owned; 116,413 Ivanhoe Electric shares were issued in the arrangement.
- Cordoba raised $26 million under its strategic arrangement with JCHX to finance the Alacran project. The cash-flow statement reports this as financing provided by non-controlling interests.
- Management said cash resources were expected to fund business plans for at least 12 months from May 8, 2024. It expects to need additional financing thereafter and cautioned that funding needs could arise earlier or planned activity could be curtailed. The company expects recurring losses and negative operating cash flow and does not expect mining revenue in the foreseeable future.
- Subsequent to quarter-end, on May 7, the company entered a three-year exploration alliance framework with BHP for U.S. areas of interest. BHP will provide initial funding of $15 million; subsequent funding is expected to be shared equally. The company will provide access to a Typhoon system.
Risks, contingencies and other items
Key risks include exploration-stage uncertainty, no mineral reserves other than at San Matias, uncertain project economics and permitting, commodity-price exposure, financing dependence, foreign-jurisdiction and joint-venture risks, and possible title, environmental and political challenges. Cordoba is involved in an ongoing criminal proceeding against former managers and a community class-action proceeding seeking an injunction related to Alacran. The company states the class-action outcome is uncertain and could materially adversely affect Cordoba; the court had not yet ruled on the requested injunction. No other legal proceedings were identified as expected to have a material adverse effect. Management reported effective disclosure controls and no material changes to internal control over financial reporting during the quarter.
Important facts for investors to verify
- Whether exploration results, permitting progress and technical studies support advancement of Santa Cruz and other projects, and how actual costs compare with plans.
- The pace of cash consumption, availability of subsidiary-held cash, and timing and terms of any additional financing.
- The status and potential consequences of Cordoba’s Alacran class action, including the requested injunction.
- Debt repayment and interest obligations, including the Santa Cruz note installments and VRB convertible bond maturity terms.
- Execution, funding terms and project selection under the BHP alliance, and the effect of acquisitions and equity awards on ownership dilution.