ORMAT TECHNOLOGIES, INC. quarterly report, Q2 FY2016

Business context and reporting period

Ormat Technologies, Inc. filed this unaudited Form 10-Q for the quarter and six months ended June 30, 2016. The company develops, owns and operates geothermal and recovered-energy power plants and sells power-generation equipment and related services. Its reporting segments are Electricity and Product. Results are compared with the corresponding 2015 periods.

Financial performance and position

MetricThree months ended June 30, 2016Three months ended June 30, 2015Six months ended June 30, 2016Six months ended June 30, 2015
Revenue$159.9 million$140.5 million$311.5 million$260.7 million
Gross margin$65.8 million; 41.2%$50.8 million; 36.1%$129.7 million; 41.6%$94.8 million; 36.4%
Operating income$51.9 million$38.6 million$102.4 million$68.5 million
Net income attributable to shareholders$24.3 million$14.4 million$53.6 million$24.4 million
Diluted EPS$0.49$0.28$1.07$0.49
  • Revenue mix: Q2 Electricity revenue was $104.0 million and Product revenue was $55.9 million. First-half amounts were $211.9 million and $99.6 million, respectively.
  • Cash flow: First-half operating cash flow was $119.6 million, versus $112.7 million in 2015. Investing used $55.3 million and financing used $57.6 million. Capital expenditures were $67.8 million.
  • Liquidity: June 30 cash and cash equivalents were $192.6 million, with an additional $38.0 million of restricted cash. Current assets were $380.2 million and current liabilities $193.1 million. Management reported $225.2 million of unused corporate borrowing capacity; $177.3 million of cash was held in foreign jurisdictions.
  • Debt and equity: Total current and long-term borrowings were approximately $871 million, including project-level limited- and non-recourse debt. Total liabilities were $1.156 billion and equity $1.117 billion. Approximately 94.4% of consolidated long-term debt was fixed-rate. About $250 million of senior unsecured bonds mature August 1, 2017.
  • Non-GAAP measure: Adjusted EBITDA was $81.2 million in Q2 and $161.5 million in the first half, compared with $67.8 million and $133.2 million, respectively, in 2015.

Material changes versus the prior comparable period

  • Q2 revenue rose 13.8%; first-half revenue rose 19.5%. First-half electricity generation increased 13.7% to 2.70 million MWh.
  • Operating income increased 34.3% in Q2 and 49.5% in the first half. The company attributed improvement primarily to higher revenue and improved Electricity segment cost efficiency, including contributions from new plant capacity.
  • First-half Product revenue increased 24.7%, driven partly by the Chile Cerro Pabellon project, which contributed about $36 million of first-half revenue. Reduced revenue from completed Turkish and other projects partly offset the increase.
  • Q2 derivative and foreign-currency transaction losses rose to $4.3 million from $0.6 million, including losses on commodity and currency contracts. First-half interest expense declined to $34.4 million from $36.7 million.
  • Cash increased by $6.6 million from year-end 2015. First-half dividends paid were $19.0 million, versus $6.8 million in the prior-year period; first-half long-term debt repayments were $31.4 million.

Outlook, commentary, risks and unusual items

  • Outlook and investment: No specific full-year revenue or earnings guidance is provided in the supplied filing text. The company estimated approximately $135 million in capital expenditures for the remainder of 2016, including development, maintenance, exploration and strategic-plan investments. It expected to fund requirements with available liquidity, operating cash flow and project financing.
  • Projects and strategic developments: The 29 MW Olkaria III Plant 4 in Kenya began commercial operation in early 2016; Veyo was brought online four months ahead of schedule. Construction began on the 35 MW Platanares project, with commercial operation expected by the end of 2017. The company also signed a roughly $36 million New Zealand supply and EPC contract and agreed to develop the 10 MW Rabbit Hill energy-storage project with Alevo.
  • Subsequent event: In July 2016, Ormat closed its acquisition of an approximately 60% interest in Guadeloupe’s Bouillante geothermal plant for about $18.6 million. It committed a further $8.4 million over two years and may owe up to $13.4 million subject to performance and expansion thresholds. After enhancements, the plant is expected to generate approximately $22.3 million in annual revenue; this is a stated expectation, not a guarantee.
  • Project risk: Sarulla, in which Ormat holds a 12.75% interest, faced field-development delays and drilling-related cost overruns. Lenders requested additional sponsor equity; sponsors agreed. First-phase operations were expected toward year-end 2016. The project had received waivers for missed milestones and was reported in compliance with revised lender milestones at June 30.
  • Market and operating risks: Although most electricity revenue came from fixed-rate PPAs, certain California and Hawaii contracts remain exposed to natural-gas or oil prices. Other stated risks include geothermal resource and plant availability, project execution, financing, regulation, foreign-country political conditions, customer concentration and competition.
  • Legal and tax matters: A qui tam lawsuit seeks approximately $375 million over alleged grant-related misconduct; the government declined to intervene and the case remained in discovery. A Chilean former representative claimed $4.6 million plus a share of certain future sales. Counties challenged energy-tax abatements valued at approximately $24.8 million in total. The company stated it believes it has defenses and intends to defend these matters. A Kenya tax audit was ongoing.
  • Other items: The company wrote off $1.4 million of unsuccessful exploration costs in the first half. It recorded a $2.1 million first-half equity loss from investees, principally Sarulla. The board declared a $0.07-per-share quarterly dividend on August 2, payable August 30, 2016. Management reported disclosure controls were effective and no material second-quarter change in internal controls.

Important facts for investors to verify

  • Whether revenue growth, generation gains and segment margins are sustainable, including the timing and margins of Product projects.
  • Liquidity availability and restrictions: foreign-held cash, the distinction between total committed borrowing capacity and unused capacity, and the 2017 bond maturity and refinancing plan.
  • Sarulla’s drilling progress, additional equity requirements, cost outlook and expected first-phase start date.
  • Actual costs, timing and performance of the 2016 capital program and the Bouillante acquisition and expansion.
  • Developments and potential financial exposure in the qui tam, Chilean, tax-abatement and other legal or regulatory matters.
  • Exposure to customer concentration, commodity prices, foreign exchange, and evolving renewable-energy policies and incentives.