TETRA Technologies is an energy services and solutions company operating on six continents through its Completion Fluids & Products and Water & Flowback Services divisions. The filing covers the quarter and nine months ended September 30, 2023. Former Compression and Offshore operations are reported as discontinued operations.
Key financial metrics
| Metric | Q3 2023 | Q3 2022 | 9M 2023 | 9M 2022 |
|---|---|---|---|---|
| Revenue | $151.5 million | $135.0 million | $473.1 million | $405.8 million |
| Gross profit | $37.9 million | $29.5 million | $123.4 million | $90.0 million |
| Gross margin | 25.0% | 21.8% | 26.1% | 22.2% |
| Income before taxes and discontinued operations | $6.7 million | $2.1 million | $35.3 million | $12.3 million |
| Net income attributable to TETRA stockholders | $5.4 million | $0.3 million | $29.7 million | $9.7 million |
| Diluted earnings per share | $0.04 | $0.00 | $0.23 | $0.08 |
| Cash flow from operating activities | Not separately provided | Not separately provided | $51.3 million | $25.9 million |
| Adjusted EBITDA | $26.1 million | Not provided in filing excerpt | Not provided in filing excerpt | Not provided in filing excerpt |
At September 30, 2023, cash and cash equivalents were $33.8 million, total debt was approximately $158.7 million on the balance sheet, and reported liquidity was $107.0 million. The ABL facility had no borrowings, $11.5 million of letters of credit and guarantees, and $68.5 million of availability, subject to borrowing-base and covenant restrictions. Total equity was $141.1 million.
Material changes versus comparable periods
- Third-quarter revenue increased 12.2% year over year, while nine-month revenue increased 16.6%.
- Nine-month gross profit increased 37.1%, and gross margin expanded to 26.1% from 22.2%, reflecting stronger pricing, product and project mix, higher activity, and cost-reduction initiatives.
- Completion Fluids & Products revenue increased 16.1% for the first nine months, with gross margin improving to 36.4% from 32.2%. Quarterly revenue declined 25.5% sequentially because of Northern European seasonality and delayed offshore projects.
- Water & Flowback Services revenue increased 17.1% for the first nine months, while gross margin increased to 15.9% from 12.0%, supported by higher activity, Latin American early production facilities, pricing, automation, and operational efficiencies.
- Nine-month interest expense increased 52.5% to $16.7 million, primarily because of higher borrowing costs and increased borrowings. The Term Credit Agreement carried an 11.68% interest rate at September 30, 2023.
- Operating cash flow nearly doubled year over year to $51.3 million. Capital expenditures were $30.2 million, including $22.0 million for Water & Flowback Services and $7.8 million for Completion Fluids & Products.
- Exploration and pre-development costs increased to $6.8 million for the first nine months, principally for lithium engineering, exploratory drilling, and appraisal work in Arkansas.
Guidance, outlook, commentary, risks, and unusual items
- The filing does not provide formal consolidated revenue or earnings guidance. Management expects demand, pricing, project timing, and seasonal patterns to continue affecting results.
- Management reported stable sequential Water & Flowback Services revenue and continued margin improvement, but noted some softness in certain U.S. land segments.
- TETRA and Saltwerx established a proposed 6,138-acre Arkansas brine unit. The Arkansas Oil & Gas Commission formally established the unit on October 17, 2023, subject to a 60-day election period for unleased parties.
- Standard Lithium delivered notice on October 6, 2023 to exercise its option to acquire lithium rights in TETRA’s Arkansas leases. The arrangement contemplates a 2.5% royalty on gross lithium revenues.
- Management expects to release an updated lithium and bromine resource report in the fourth quarter and an initial economic assessment for a lithium extraction plant in early 2024, subject to engineering progress. Development requires additional resource, pre-feasibility or feasibility work and capital commitments.
- Third-quarter exploration and pre-development expense was $3.8 million. Saltwerx reimbursements credited $6.7 million during the first nine months and $1.9 million during the third quarter, contributing to other income.
- A $0.8 million impairment of the corporate office lease was recorded in the second quarter. The company also has approximately $74.9 million of fixed and determinable product purchase obligations extending through 2028.
- The Argentina credit facility, which had $1.9 million outstanding at September 30, 2023, expired and was repaid in October 2023. The Swedish facility expires December 31, 2023, and the Finland credit agreement expires January 31, 2024; management intends to renew them annually.
- Risks include high interest expense, floating-rate debt exposure, borrowing-base volatility, customer collection risk, foreign exchange movements, industry cyclicality, execution and commercialization risk for lithium and bromine projects, and possible limitations on use of tax attributes.
- The Tax Benefits Preservation Plan, ratified by stockholders in May 2023, is intended to protect net operating losses and other tax attributes but may restrict certain acquisitions of common stock and could affect stock marketability.
- Management stated that it was in compliance with all debt covenants and that no material adverse litigation exposure was considered reasonably possible beyond accrued amounts.
Important facts for investors to verify
- Reconcile reported liquidity of $107.0 million to cash, ABL availability, and other facility availability, including the effects of the October repayment of the Argentina facility.
- Review the Term Credit Agreement’s 11.68% interest rate, September 2025 maturity, security package, and excess-cash-flow prepayment requirements.
- Assess whether the quarterly revenue decline and margin compression versus the second quarter are seasonal or indicate broader demand or project-timing weakness.
- Validate the economics, ownership arrangements, royalty terms, regulatory status, and funding requirements for the Arkansas lithium and bromine projects.
- Monitor the Standard Lithium option exercise, the Saltwerx brine-unit arrangements, unleased-party elections, and future reimbursement or development obligations.
- Evaluate the sustainability of earnings after excluding collaborative-arrangement reimbursements, investment fair-value changes, discontinued operations, and other unusual items.
- Review the approximately $74.9 million of purchase obligations, capital expenditure needs, debt refinancing requirements, and potential cash-tax impact if NOLs cannot be utilized.