Fabric.AI, Inc. quarterly report, Q3 FY2012

Business Context and Reporting Period

The filing is a Form 10-Q for WPCS International Incorporated, not Fabric.AI, Inc. It covers the quarter and nine months ended January 31, 2012, within the fiscal year ending April 30, 2012. WPCS provided design-build engineering services for communications infrastructure across wireless communications, specialty construction and electrical power markets.

The company had approximately 450 employees across seven operating centers on three continents. The St. Louis and Sarasota operations were sold on September 1, 2011 and are presented as discontinued operations.

Key Financial Metrics

MetricThree months ended January 31, 2012Three months ended January 31, 2011Nine months ended January 31, 2012Nine months ended January 31, 2011
Revenue$20.5 million$21.4 million$72.2 million$67.9 million
Operating loss$(5.5) million$(3.6) million$(5.4) million$(11.2) million
Net loss attributable to WPCS$(10.3) million$(3.5) million$(12.0) million$(9.8) million
Basic and diluted loss per share$(1.48)$(0.50)$(1.73)$(1.41)
Net cash from operating activitiesNot separately providedNot separately provided$1.6 million$0.2 million
  • Third-quarter cost of revenue was $19.9 million, or 97.2% of revenue, versus 79.1% in the prior-year quarter. Nine-month cost of revenue was 84.5% versus 80.8%.
  • Third-quarter operating margin was approximately negative 26.8%; nine-month operating margin was approximately negative 7.4%.
  • Third-quarter SG&A was $5.5 million, or 26.8% of revenue. Nine-month SG&A was $14.8 million, or 20.5% of revenue.
  • Cash and cash equivalents were $1.7 million at January 31, 2012, compared with $4.9 million at April 30, 2011.
  • Working capital was approximately $6.8 million, based on current assets of $29.6 million and current liabilities of $22.8 million.
  • Total assets were $37.7 million and total liabilities were $23.2 million at January 31, 2012. Total equity was $14.5 million.
  • Accounts receivable, net, were $22.2 million, with an allowance for doubtful accounts of approximately $1.5 million.
  • Operating activities generated $1.6 million of cash during the first nine months. Investing activities generated $0.3 million, while financing activities used $5.0 million, resulting in a $3.1 million decrease in cash.
  • Debt included $3.1 million outstanding under a revolving credit facility, approximately $0.4 million of loans and capital lease obligations, and $3.1 million owed to the China joint venture partner.

Material Changes Versus the Prior Comparable Period

  • Nine-month revenue increased 6.4% to $72.2 million, but third-quarter revenue declined 4.4% to $20.5 million. Management attributed the quarterly decline primarily to revised estimates on three Trenton projects and project delays.
  • Excluding the three Trenton projects, management stated that revenue increased approximately 10.5% in the quarter and 11.0% for the nine months.
  • Estimated profits on three Trenton projects were reduced by approximately $5.0 million in the third quarter, including approximately $4.0 million on an electrical project with an approximately $14.4 million contract value whose estimated total cost increased to approximately $16.0 million.
  • The company recorded a $1.0 million provision for anticipated losses on certain uncompleted contracts. Contract-estimate revisions reduced reported gross profit by approximately $4.8 million in the quarter and $3.1 million for the nine months.
  • Trenton generated EBITDA losses of approximately $4.7 million in the quarter and $4.5 million for the nine months. Excluding Trenton, the remaining operations generated approximately $0.3 million of quarterly EBITDA and $3.0 million of nine-month EBITDA, compared with $0.2 million and an EBITDA loss of $0.1 million, respectively, in the prior-year periods.
  • The company established a full valuation allowance of approximately $6.7 million against U.S. federal and state deferred tax assets. This produced an income tax provision of $4.6 million in the quarter and $4.7 million for the nine months despite pretax losses.
  • Prior-year periods included goodwill and intangible-asset impairment charges of $2.6 million in the quarter and $6.9 million for the nine months; no comparable impairment charge was recorded in 2012.
  • The St. Louis and Sarasota sale resulted in a nine-month discontinued-operations loss of $1.3 million, including a $1.0 million loss on disposal and approximately $0.3 million of sale-related expenses.
  • SG&A declined 3.3% for the nine months, primarily due to lower salaries, commissions and strategic-alternatives costs, although quarterly SG&A increased 12.4%.

Liquidity, Debt, Outlook and Risks

  • On January 27, 2012, WPCS entered into a secured revolving credit agreement with Sovereign Bank providing for up to $12.0 million of revolving borrowings and a $2.0 million letter-of-credit facility. Borrowings were subject to a borrowing base and secured by substantially all domestic assets and pledged equity interests.
  • At January 31, 2012, total availability under the facility was $6.4 million, outstanding borrowings were $3.1 million and net availability was approximately $3.3 million. The facility expires January 26, 2015 and initially bears interest at LIBOR plus 2.75%, or approximately 3.02% at January 31, 2012.
  • The company met its leverage-ratio covenant at January 31, 2012, but expected not to meet the 1.2-to-1 fixed-charge-coverage covenant when first tested for the two quarters ending April 30, 2012. The potential covenant failure is a material liquidity risk.
  • Management stated that cash requirements were expected to be met through the Sovereign facility, working capital and expense management, and believed sufficient capital was available for the next twelve months. The filing nevertheless states that the financial statements were prepared on a going-concern basis.
  • Approximately $3.1 million owed to the China joint venture partner included $2.4 million maturing September 30, 2012 and $0.7 million due on demand. Management expected renewal of unpaid balances based on historical support, but renewal was not assured.
  • Backlog declined to approximately $27.5 million at January 31, 2012 from $30.2 million at October 31, 2011 and $30.7 million at January 31, 2011. The bid list increased to approximately $192 million from $163 million at October 31, 2011.
  • Management expected consolidated EBITDA to be profitable in the fourth quarter ending April 30, 2012 and expected Trenton to return to profitability in fiscal 2013. These are management expectations, not guarantees.
  • Material risks include project-cost overruns, estimation uncertainty under percentage-of-completion accounting, project delays or cancellations, customer collections, competition, material costs, international operations, covenant compliance and the ability to raise additional equity.
  • Multiband terminated discussions to acquire WPCS on January 31, 2012. WPCS received a $250,000 break-up fee and ended its strategic-alternatives initiative.
  • A shareholder derivative and putative class-action lawsuit related to the terminated Multiband transaction remained pending; management expected dismissal after the transaction was abandoned.

Important Facts for Investors to Verify

  • Confirm that the filing relates to WPCS International Incorporated and the January 31, 2012 reporting period, rather than Fabric.AI, Inc. or a 2011 third-quarter filing.
  • Verify the status of the expected fixed-charge-coverage covenant failure, including any waiver, amendment, default or acceleration under the Sovereign credit agreement.
  • Track completion costs, remaining exposure and cash requirements for the three Trenton projects, particularly the electrical project whose estimated cost exceeded its contract value.
  • Assess whether operating cash flow and the approximately $3.3 million of net revolver availability are sufficient given cash of only $1.7 million and current obligations.
  • Verify renewal or repayment arrangements for the approximately $3.1 million owed to the China joint venture partner.
  • Compare subsequent backlog conversion and bid awards with the reported $27.5 million backlog and $192 million bid list.
  • Evaluate the recoverability of deferred tax assets and whether additional valuation allowances or tax charges may be required.
  • Review the final disposition of the shareholder litigation and any remaining costs or claims related to the terminated Multiband transaction.
Disclaimer:
This AI-generated summary by MetaQuotes is based on SEC filings and may contain errors. Verify important details against the original SEC filings.