Reporting period: Fiscal year ended December 31, 2014; comparisons are with FY2013. The filing was signed April 2, 2015. The company manufactures and services electrical transformers, switchgear, on-site power-generation equipment and related services, across T&D Solutions and Critical Power Solutions. This is an annual report, not a standalone Q4 report.

Financial performance

MetricFY2014FY2013
Revenue$92.2 million$88.2 million
Gross profit / margin$18.2 million / 19.7%$21.8 million / 24.7%
Operating income$1.8 million$7.1 million
Net income (loss)$(0.3) million$5.3 million
Diluted EPS$(0.04)$0.84
Cash from operating activities$0.1 million$3.2 million
Capital expenditures$0.7 million$2.7 million
  • Revenue and segments: Consolidated revenue rose 4.6%. T&D revenue was $85.9 million, down 1.2%; Critical Power revenue was $6.3 million, up from $1.3 million, reflecting acquisitions and project activity. Titan contributed only December results.
  • Margins and earnings: Gross profit fell 16.5%, primarily from weaker Canadian transformer sales and mix, pricing pressure, lower production throughput and costs in Critical Power project packages. Operating income declined 75.5%. Net loss reflected lower gross margin, $1.4 million of non-cash Bemag impairment charges and higher acquisition-related expense.
  • Cash flow and liquidity: Cash and equivalents were $3.8 million at year-end, versus $0.4 million. Working capital was $9.7 million, down from $13.8 million; the current ratio fell to 1.4 from 2.1. Operating cash flow was nearly breakeven, with working capital consuming cash.
  • Debt: Total debt was approximately $18.9 million, versus $10.1 million a year earlier, including $12.0 million of long-term debt and $6.9 million of revolving borrowings. The increase was principally associated with Titan and related financing. The company reported compliance with its credit-facility covenants at year-end. Substantially all assets secure borrowings.
  • Backlog: Year-end backlog was $36.0 million, up from $24.4 million; management expected most to be delivered during 2015. Backlog is not guaranteed revenue and may be canceled.

Material changes and unusual items

  • T&D transformer revenue declined 5.9%; Canadian sales fell, partly offset by U.S. growth in OEM solutions. Critical Power growth reflected more large paralleling-switchgear projects and the December acquisition of Titan.
  • In Q4, the company recorded $1.4 million of non-cash impairment charges for Bemag goodwill and intangible assets amid weaker natural-resource demand, lower oil prices, Canadian-dollar depreciation, higher input costs, competition and customer insolvencies. Bemag’s remaining goodwill was written down; remaining goodwill and intangible assets were reported at $0.8 million.
  • The company identified $0.9 million of prior-period cost-of-goods-sold errors originating in 2014 interim periods and corrected them in Q4. Management concluded the errors were immaterial to the quarterly and annual statements; the correction reduced FY2014 pretax earnings by $0.9 million and net earnings by $0.6 million.
  • The effective tax rate was 205%, largely because the impairment charges were nondeductible. Management said the rate would have been 31.6% excluding those charges. FY2013 included a $1.0 million tax benefit from a Canadian legal-entity amalgamation.
  • Foreign-currency translation reduced other comprehensive income by $1.7 million in FY2014. Approximately 49% of FY2014 revenue was denominated in Canadian dollars.

Outlook, risks and contingencies

  • Management stated a goal of doubling revenue and operating margin over the next two to four years through internal growth and acquisitions. This is a strategic goal, not formal numerical guidance; the filing provides no specific FY2015 earnings or revenue forecast.
  • Management expected most backlog to ship in 2015 and reported no major capital projects planned for 2015 beyond continuing ERP deployment. It believed available working capital, borrowing capacity, operating cash flow and cash on hand would meet anticipated needs for at least 12 months.
  • On March 27, 2015, the company prepaid CAD $5.0 million (about $4.0 million) of Canadian Facility C and amended its U.S. credit-facility covenants. The amendments adjusted covenant calculations and permitted extraordinary expenses to be included in EBITDA, subject to specified limits.
  • Key risks include dependence on Hydro-Quebec and Siemens, which accounted for approximately 13% and 10% of FY2014 sales, respectively; customer and project concentration; Canadian-dollar movements; raw-material costs; competitive pricing; labor and supply risks; and restrictive, borrowing-base-dependent credit facilities. The Hydro-Quebec supply agreement was renewed in February 2015, but does not require minimum purchases.
  • Management concluded disclosure controls and internal control over financial reporting were ineffective at year-end because of material weaknesses involving entity-level controls and financial reporting, Bemag inventory, and Pioneer Critical Power’s close and project-costing processes. A remediation plan was underway; management had not established that the weaknesses were remediated.
  • The company reported no material pending legal proceedings and no material off-balance-sheet arrangements other than operating leases. It reported $2.1 million of future operating-lease commitments.

Most important facts for investors to verify

  • Whether the internal-control material weaknesses were remediated and whether subsequent filings required corrections or restatements.
  • Whether gross margins and operating performance recover, especially in Canadian T&D and Bemag, and whether the impairment assumptions prove reasonable.
  • Whether the $36.0 million backlog converts to revenue and cash on expected timing and terms.
  • Debt levels, borrowing-base availability, covenant headroom and the impact of the March 2015 prepayment and amendments.
  • Customer exposure, including actual Hydro-Quebec and Siemens orders, and the renewal and performance terms of key customer and Generac agreements.
  • Titan’s ongoing contribution and integration results; FY2014 includes only one month of Titan revenue and expenses.