BWX Technologies, Inc. annual report, FY2012

Business Context and Reporting Period

The filing is The Babcock & Wilcox Company’s Form 10-K for the fiscal year ended December 31, 2012, filed February 27, 2013. The company operates four segments: Power Generation, Nuclear Operations, Technical Services, and Nuclear Energy. Its businesses are project-oriented, capital-intensive, and substantially exposed to U.S. Government and utility spending.

The company provides fossil-fuel and renewable-fuel power systems, emissions-control equipment, naval nuclear components and fuel, U.S. Government nuclear and environmental services, commercial nuclear components, and development of the B&W mPower small modular reactor.

Key Financial Metrics

Metric20122011Change
Revenue$3.291 billion$2.952 billion+11.5%
Operating income$346.6 million$95.7 million+$250.9 million
Income before tax$319.4 million$94.5 million+$224.9 million
Net income attributable to company$227.7 million$78.3 million+190.8%
Diluted EPS$1.91$0.66+189.4%
Effective tax rate31.9%25.3%Higher
Cash flow from operations$184.9 million$173.6 million+$11.3 million
Capital expenditures$86.6 million$63.9 million+$22.8 million

Operating income as a percentage of revenue was approximately 10.5%, compared with 3.2% in 2011. Net income attributable to the company was approximately 6.9% of revenue, compared with 2.7% in 2011. These comparisons are affected by the retrospective pension-accounting change and significant 2011 project charges.

Segment Results

Segment2012 Revenue2012 Operating IncomeChange versus 2011
Power Generation$1.786 billion$183.4 millionRevenue +15.9%; income essentially flat
Nuclear Operations$1.098 billion$226.3 millionRevenue +5.3%; income +$31.9 million
Technical Services$107.9 million$59.7 millionRevenue -9.9%; income -$10.2 million
Nuclear Energy$326.0 million$(62.9) millionLoss improved by $54.0 million
  • Backlog was $5.749 billion at December 31, 2012, up from $5.339 billion. Power Generation backlog was $2.483 billion, Nuclear Operations $2.984 billion, Technical Services $4 million, and Nuclear Energy $278 million.
  • Approximately $3.0 billion, or 52% of total backlog, was with the U.S. Government; $180.6 million had been awarded but not funded.
  • Cash, restricted cash, and investments totaled approximately $540.3 million at year-end. Management defined total liquidity as $1.0185 billion, including available credit capacity.
  • The company had no borrowings under its $700 million revolving credit facility and had $542.1 million available after letters of credit. Total debt was approximately $4.5 million, including current maturities.
  • Working capital increased to $441.8 million from $332.3 million. Total assets were $2.840 billion and stockholders’ equity was $1.003 billion.
  • At December 31, 2012, the company had $217.3 million of letters of credit and bank guarantees and $468.6 million of surety bonds outstanding.
  • The company declared and paid a fourth-quarter dividend of $0.08 per share and repurchased 3.9 million shares for approximately $96.7 million during 2012. The board authorized up to $250 million of repurchases.

Material Changes Versus the Prior Comparable Period

  • Revenue growth was led by Power Generation’s new-build environmental equipment and steam-generation systems and by higher Nuclear Operations activity.
  • Nuclear Operations profitability improved through better performance on U.S. Government nuclear-component programs and higher naval-fuel and downblending activity.
  • Nuclear Energy’s operating loss narrowed primarily because 2011 included approximately $50.7 million of costs to complete the Columbia Generating Station condenser project. The 2012 results included approximately $18.4 million of revenue from a related claims settlement, with approximately $18.1 million of net income after related expenses.
  • Technical Services declined because of lower award fees, reduced American Centrifuge work, and lower Fukushima-related support activity.
  • Power Generation margins were pressured by competition and the early phase of the environmental-equipment cycle, despite strong revenue growth.
  • Other expense included a $27.0 million impairment of the USEC preferred-stock investment. The investment was written down to an estimated fair value of $19.1 million.
  • The company changed its pension and other postretirement accounting method to recognize actuarial gains and losses immediately in fourth-quarter earnings. The change was applied retrospectively and reduced reported 2012 operating income by approximately $31.9 million, compared with a $215.4 million pension-related reduction in 2011 under the new presentation.
  • Research and development activities totaled $173.9 million, including $120.6 million expensed by the company and $53.4 million funded by customers. Spending increased from $163.0 million in 2011, primarily reflecting continued mPower development.

Guidance, Outlook, Risks, and Unusual Items

  • Management expected 2012 year-end backlog to produce approximately $1.2 billion of 2013 Power Generation revenue, $1.1 billion of Nuclear Operations revenue, and $180 million of Nuclear Energy revenue, excluding change orders and new awards.
  • Management expected Power Generation’s environmental cycle to extend to approximately six or seven years, rather than the previously expected three to four years, because of regulatory uncertainty, low natural-gas prices, and economic conditions.
  • Technical Services operating income was expected to decline in 2013 because of a revised fee structure or possible loss of the combined Y-12/Pantex contract. A company-led joint venture was not selected for the contract in January 2013 and filed a protest.
  • The Y-12 facility experienced a security breach in 2012, temporarily disrupting operations and reducing 2012 fees. Security responsibilities and leadership arrangements were subsequently changed.
  • The company planned to maintain mPower development spending at approximately 2012 levels, excluding additional third-party or DOE funding. Commercialization depends on successful development, funding, and NRC certification.
  • Major risks include dependence on U.S. Government appropriations, defense-budget reductions and sequestration; utility capital spending and environmental regulation; fixed-price contract losses; project delays and liquidated damages; supply-chain constraints; nuclear, environmental, cybersecurity, insurance, and litigation exposures; and risks associated with joint ventures.
  • The defined-benefit pension and postretirement plans were underfunded by approximately $731.2 million. Expected 2013 pension contributions were approximately $75.3 million, with an additional $13.3 million for other postretirement plans.
  • Environmental reserves were $49.6 million at year-end, and 2012 environmental compliance generated $15.3 million of pretax charges and $3.2 million of capital expenditures. Potential future remediation costs may exceed recorded reserves.
  • The company disclosed approximately $6.0 million of potential liquidated damages on a Power Generation project that had not been accrued because management believed the damages were not probable; the outcome of customer discussions remained uncertain.
  • Pending litigation included the Apollo and Parks matters involving alleged radioactive releases and an appeal in the ANI insurance-reimbursement litigation. The company had not recognized amounts claimed in the ANI matter because realization remained uncertain.

Investor Verification Checklist

  • Verify the sustainability of 2012 profitability after excluding the pension-accounting change, the Energy Northwest settlement, the USEC impairment, and the unusually high 2011 project charges.
  • Review the status and financial impact of the Y-12/Pantex contract protest and any resulting transition costs or lost fees.
  • Assess the portion of backlog that is funded, expected timing of conversion to revenue, and potential cancellations, scope changes, or margin erosion.
  • Monitor U.S. Government appropriations, sequestration, defense spending, and DOE/NNSA contract renewals.
  • Evaluate Nuclear Energy’s continuing losses, mPower funding requirements, NRC licensing prospects, and commercialization timetable.
  • Review pension funding requirements, plan assumptions, and the effect of future interest rates and asset returns on earnings and liquidity.
  • Assess fixed-price contract exposures, the unaccrued liquidated-damages claim, environmental reserves, nuclear liabilities, insurance coverage, and pending litigation.
  • Confirm the company’s share-repurchase pace, dividend restrictions under the credit agreement, and availability of revolving-credit and bonding capacity.