Cheniere Energy Partners, L.P. quarterly report, Q1 FY2007

Business Context and Reporting Period

Company: Cheniere Energy Partners, L.P. (a Delaware limited partnership)

Reporting Period: Quarter ended March 31, 2007

Business Stage: Development stage enterprise. The partnership was formed to develop, own, and operate the Sabine Pass LNG receiving terminal in Louisiana. As of the reporting date, the company had no operating revenues and was focused entirely on construction activities. Commercial operations are not expected until the second quarter of 2008.

Key Event: The company completed its Initial Public Offering (IPO) on March 26, 2007, issuing 5,054,164 common units to the public at $21.00 per unit.

Key Financial Metrics

Metric Three Months Ended Mar 31, 2007 Three Months Ended Mar 31, 2006
Revenues $0 $0
Total Expenses $1.9 million $1.6 million
Net Loss $(12.9) million $(0.8) million
Cash Used in Operating Activities $(0.3) million $(3.2) million
Cash Used in Investing Activities $(97.5) million $(62.0) million
Cash Provided by Financing Activities $97.8 million $65.2 million
Long-Term Debt $2.032 billion $2.032 billion
Total Assets $2.014 billion $1.858 billion
Restricted Cash & Equivalents $1.105 billion $1.159 billion

Note: The company reported a cumulative deficit of $85.3 million from inception through March 31, 2007.

Material Changes vs. Prior Period

  • Net Loss Increase: Net loss increased to $12.9 million from $0.8 million in the prior year quarter. This was driven primarily by a significant increase in interest expense ($25.8 million) due to the outstanding Sabine Pass LNG notes, partially offset by higher interest income ($14.8 million) from restricted cash reserves.
  • Operating Expenses: Total operating expenses rose 19% to $1.9 million, primarily due to increased labor and overhead charges from affiliates following the IPO and secondment of employees.
  • Capital Expenditures: Investing cash outflows increased to $97.5 million, reflecting $73.0 million in LNG terminal construction and $98.4 million invested in restricted treasury securities to fund the distribution reserve.
  • Financing: Financing cash inflows increased to $97.8 million, largely due to $98.4 million in net proceeds from the IPO. In the prior period, financing was driven by credit facility borrowings.

Outlook, Guidance, and Risks

  • Construction Timeline: The company anticipates commencing commercial operations in the second quarter of 2008. Phase 1 construction costs are estimated at $900–$950 million; Phase 2-Stage 1 is estimated at $500–$550 million.
  • Liquidity and Distributions: Net IPO proceeds ($98.4 million) were invested in U.S. Treasury securities to fund a distribution reserve. This reserve is intended to pay quarterly distributions of $0.425 per common unit through June 30, 2009. After this date, distributions will depend on operating cash flows.
  • Debt Service: The company holds $2.032 billion in senior secured notes. Interest payments are funded by a reserve account of approximately $335 million. Distributions to unitholders are restricted until specific construction milestones and debt service coverage ratios are met.
  • Customer Commitments: Long-term Terminal Use Agreements (TUAs) are in place with Total, Chevron, and Cheniere Marketing for 4.0 Bcf/d of capacity, providing future revenue visibility once operations begin.
  • Risks: Key risks include construction cost overruns, delays in completion, regulatory approvals, and the potential need for additional financing if the option for a sixth LNG storage tank is exercised by Cheniere Marketing.

Investor Verification Checklist

  • Verify the status of the Sabine Pass LNG terminal construction against the Q2 2008 commercial operation target.
  • Confirm the sufficiency of the $98.4 million distribution reserve to cover quarterly payments through June 2009, including interest earnings.
  • Monitor the $2.032 billion debt service obligations and the status of the interest reserve account.
  • Review the progress of the SEC investigation into Cheniere Energy (parent company) mentioned in the legal proceedings section.
  • Assess the potential impact of the Cheniere Marketing option for a sixth LNG storage tank (estimated cost $120–$140 million) on future capital requirements.