GORMAN RUPP CO quarterly report, Q1 FY2024

The Gorman-Rupp Company — Q1 2024 10-Q

Business and period: Pump and pump-system designer and manufacturer. This unaudited report covers the three months ended March 31, 2024; comparisons are with Q1 2023 unless stated otherwise. Amounts below are in U.S. dollars.

Financial performance

MetricQ1 2024Q1 2023Change
Net sales$159.3 million$160.5 millionDown 0.7%
Gross profit / margin$48.4 million / 30.4%$45.5 million / 28.4%Margin up 2.0 points
Operating income / margin$20.4 million / 12.8%$19.1 million / 11.9%Income up 7.0%
Net income$7.9 million$6.5 millionUp 20.9%
Diluted earnings per share, as reported$0.30$0.25Up $0.05
Cash from operations$10.7 million$18.6 millionDown $7.9 million

Gross-margin improvement reflected lower material costs, selling-price increases, lower LIFO expense and the absence of prior-year acquired-backlog amortization; higher labor and overhead partly offset these benefits. SG&A rose 7.1% to $24.9 million, primarily to support sales growth. Interest expense was $10.1 million, broadly stable year over year. The effective tax rate was 21.8%, versus 23.1%.

Liquidity, debt and cash flow

At March 31, cash was $27.8 million. Total debt was $409.4 million ($400.7 million net of unamortized discount and issuance fees), including $24.1 million current and $376.7 million long-term debt on the balance sheet. The company reported $98.7 million available on its revolving facility after letters of credit and said it expects adequate liquidity for at least 12 months. Debt is principally variable-rate, with maturities in 2027; the company was in covenant compliance.

Operating cash flow fell to $10.7 million, which management attributed primarily to increased working-capital needs. Capital expenditures were $3.9 million; investing cash use was $3.9 million. Financing cash use was $9.4 million, mainly debt repayments and $4.7 million of dividends. Cash declined $2.7 million during the quarter to $27.8 million.

Changes, outlook and risks

  • Sales were mixed by end market: municipal sales increased 16.1%, while fire sales declined 10.6%; domestic sales rose 1.1% and international sales fell 6.2%.
  • Orders reached a quarterly record $178.9 million, up 7.1%. Backlog increased during the quarter to $234.2 million, but was below $270.6 million a year earlier. Management expects backlog to return to more normal levels by year-end and remains optimistic about full-year profitable growth. Substantially all reported remaining performance obligations are expected to be recognized within one year.
  • Planned 2024 capital expenditures are $18–$20 million, expected to be funded with internally generated cash. A $0.18-per-share dividend was authorized after quarter-end, payable June 10, 2024.
  • Interest-rate exposure remains significant: management estimates a 100-basis-point rate increase would add approximately $2.5 million to annual interest expense. Swaps hedge a portion of the senior term loan; $159.7 million notional was outstanding at a 4.1% average fixed rate, with terms extending to May 2027.
  • Disclosed risks include variable-rate indebtedness and debt repayment, economic and supply-chain conditions, raw-material and labor costs, acquisition integration and realization of Fill-Rite benefits, goodwill and intangible-asset impairment, foreign-exchange exposure, cybersecurity, regulatory and environmental compliance, and pension and LIFO-related changes. The Fill-Rite pension plan was frozen effective January 31, 2024 and was scheduled to terminate April 30, 2024.

Management’s adjusted EPS was $0.30 versus $0.27 in Q1 2023; this non-GAAP comparison excludes acquired customer-backlog amortization. No material change in previously reported legal proceedings was disclosed, and disclosure controls were assessed as effective.

Investor facts to verify

  • Whether record order intake converts to revenue and how backlog develops against management’s year-end normalization expectation.
  • Whether gross-margin gains persist as pricing, material costs, labor and overhead evolve, and whether lower operating cash flow rebounds as working-capital needs change.
  • Debt-service capacity and covenant headroom under variable rates, including the effect of the subordinated facility’s SOFR-plus-9.1% rate and the extent of effective hedge protection.
  • Progress on Fill-Rite integration and the pension-plan termination, and any related costs or benefit realization.
  • Execution of the $18–$20 million capital-spending plan and continued dividend capacity given debt, cash generation and liquidity.