Regulation FD Disclosure

Halliburton Company — Form 8-K Summary

Filing date: October 14, 2004. Reported event: October 13, 2004 (Items 7.01 and 8.01). This filing reports a project milestone and revised agreement in principle; it does not provide company-period financial statements.

Business context and project update

Halliburton’s KBR subsidiary is managing the Barracuda-Caratinga offshore development in Brazil for the project company, with Petrobras acting as Construction Manager. The project includes two floating production, storage and offloading vessels (FPSOs), wells, subsea pipelines and related facilities.

  • Barracuda FPSO P-43 left the Maua-Jurong shipyard on October 13 for sea trials and final inspections, before proceeding to the Campos Basin for mooring, hook-up and commissioning.
  • First oil from Barracuda was expected in early November 2004. Caratinga FPSO P-48 was under conversion in Brazil, with departure scheduled for December 2004 and production expected in January 2005.
  • The fields cover 493 square kilometers in water depths of 800 and 1,035 meters. Together, they were expected to produce close to 300,000 barrels of oil per day and each vessel was designed to store about two million barrels.

Financial and operating metrics

  • KBR’s project contract was valued at $2.5 billion and covered engineering, procurement, installation and construction, including 54 wells, pipelines, FPSOs, commissioning, start-up and operations support.
  • The filing says the wells were drilled within an approximately $1 billion budget, on schedule and at expected productivity and injectivity rates. It does not clarify the scope of that budget beyond the wells.
  • The filing provides no Halliburton revenue, profit, cash flow, margin, debt or liquidity figures, and no comparable-period financial results.
  • Project progress cited includes 54 wells drilled and completed (34 Barracuda and 20 Caratinga) and more than 400 kilometers of flexible subsea pipelines installed.

Material changes, outlook and risks

KBR reached a revised agreement in principle with Petrobras to resolve outstanding Barracuda-Caratinga issues. It replaces the non-binding agreement reached in April 2004 and contemplates settling outstanding claims, extending project deadlines, amending existing agreements and releasing both parties from existing claims.

The revised agreement remained subject to project lender approval and execution of a final agreement. If the parties do not reach a final agreement, Halliburton said it would pursue arbitration of its claims. The filing does not disclose settlement amounts or revised deadline dates.

Management described P-43’s departure as a significant project milestone. The production dates and volumes are expectations, not reported results; commissioning, project completion and the agreement remain subject to the conditions described in the filing.

Most important facts for investors to verify

  • Whether lenders approved and the parties executed the revised Petrobras agreement, including its financial and deadline terms.
  • Whether Barracuda and Caratinga reached the stated commissioning and first-oil schedules, and whether expected production was achieved.
  • Whether further project costs, claims or arbitration affected Halliburton’s financial results; this filing does not quantify their potential impact.